Resolved
Decision Members noted the information provided.
Rothesay CHORD Project Board noted this item on Wednesday 30 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Members noted the information provided.
HIGHLIGHT / PROGRESS REPORT PROJECT NAME: ROTHESAY THI Project Manager: AUDREY MARTIN Reporting Period: 24/11/2010 – 30/03/2011 Date report prepared: 24/03/2011 30/03/11 (as all funding has now been Project stage: Preparation of Full Business Case Project stage completion date: secured the project will now begin to move into the implementation stage)
Tolerance levels for this stage: Project Plan + / - 15 working days Project budget + / - 10%, or £10,000 whichever is greater
Key products completed this period Key products outstanding this period Revised Key products for next reporting Delivery date (including those completed ahead of schedule) (including brief explanation of why product delivery date period outstanding) HS CARS funding approved Preparatory work being prepared This is for the start up meeting with HLF dependent on HLF Stage two approval secured which we hope will be held end of date of meeting April/beginning of May. with HLF but Leader + funding approved. This work includes preparing we are aiming application forms, grants to start the conditions, job descriptions, project June adverts, launch details 2011 Dependent on information Expressions of interest have been being received submitted relative to the Gap site in and case being Guildford Square and these are made by currently under consideration interested parties
Risk Management – please refer to Risk Register Risk Ref. Risk Current status Previous Revised RAG status RAG status RY01_R003 Heritage Lottery Fund Stage two bid fails Working with HLF to minimise risk 16 0 RY01_R010 Cost escalation and over-run - Poor Detailed costings are much higher than originally estimated and 16 0 estimates of project costs. this may well mean that we cannot achieve what we originally anticipated. Looking at VAT rates for each of the individual
d:\moderngov\data\published\intranet\c00000395\m00004585\ai00058335\ry01highlightprogrepmarch110.doc components of the project as this may help with budget. Also removal of some elements from project. RY01_R04 Unable to secure match funding. CARS bid is essential to ensuring we have sufficient match 16 0 funding to achieve a successful THI/CARS project. Working with HS to minimise risk however looks like £500, 000 would be maximum level and had to amend bid accordingly
Budget Management – please refer to Resource Allocation Schedule Total budget available to complete this stage: £123,500 (plus an additional £50,000 development monies from HLF) Forecast expenditure for current financial year Actual expenditure to date Variance explanation if required: £ £ £131, 575.25 (28.02.2011)
Any further information
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Rothesay THI: Highlight / Progress ReportReport | 57 KB | DownloadRead as text |
Follow Rothesay CHORD Project Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2014 | Appointment of chair of new organisationDecision The Board agreed to offer the post of Chair of the new Charity Board to the candidate recommended by the int... | Agreed | Open |
| 20 Mar 2013 | Rothesay Pavilion - Highlight/Progress ReportDecision The Board noted the information provided. (Reference: Report by the Project Manager dated 11 th March 2013 –... | Noted | Open |
| 20 Mar 2013 | Rothesay Pavilion - Project Programme UpdateDecision The Board noted the information provided. (Reference: Report by the Project Manager dated 14 th March 2013 –... | Noted | Open |
| 20 Mar 2013 | Rothesay Pavilion - Governance StrategyDecision The Board agreed:- To note the information provided and agreed that the Scottish Charitable Incorporated Org... | Agreed | Open |
| 20 Mar 2013 | Creative Community Steering Group - Public Open Evening Wednesday 20th March & HI Arts Events Thursday 21st MarchDecision The Board noted the information provided. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.