Decision The Board agreed that:- i. The Rothesay THI project is governed as detailed in paragraph 3.2 of the report by the Head of Economic Development. ii. Bute Conservation Trust acts as a Steering Group for Rothesay THI. (Reference: Report by the Head of Economic Development – submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This paper proposes the governance arrangements for the implementation phase of the Townscape Heritage Initiative (THI).
Recommendations
2.1That the Rothesay CHORD Project Board agree that:
a) the Rothesay THI project is governed as detailed in paragraph 3.2 of this report, and; b) Bute Conservation Trust acts as a Steering Group for Rothesay THI.
3. DETAIL
3.1Rothesay has been successful in attracting grant assistance from two separate heritage based regeneration schemes: Historic Scotland’s Conservation Area Regeneration Scheme and Heritage Lottery Fund’s Townscape Heritage Initiative. Both are grant schemes administered by Argyll and Bute Council under the banner Rothesay THI.
3.2The following arrangements are proposed for the implementation phase of this project:
a) Officers will authorise grants up to the value of £5,000 (five thousand pounds); b) Bute Conservation Trust will act as the Steering Group and will consider applications at their regular meetings. The recommendation from these meetings will be brought to the Rothesay CHORD Project Board for decision; c) Should urgent decisions be required in this regard, the core members of the Rothesay CHORD Project Board can be contacted via email in order that there is no delay to the progression of projects; d) The Chair of the Rothesay CHORD Project Board can call a meeting to discuss matters in connection with the Rothesay THI project, if necessary; e) At relevant meetings of the Rothesay CHORD Project Board, an update report on Rothesay THI will be presented which will include the recommendations from the steering group, Bute Conservation Trust, on grant awards; f) Rothesay CHORD Project Board will be asked to consider Small Building Repair grants once a year, in January.
3.3The Project Officer, Lorna Pearce, and Project Manager, Audrey Martin, for Rothesay THI will advise the Steering Group of the decision made by the Rothesay CHORD Project Board and will ensure that any changes to existing administrative arrangements are made to reflect the decision.
3.4It should be noted that the arrangements described above are based on the model used in Campbeltown THI which has been working well over the last year. 4. IMPLICATIONS
POLICY The delivery of the CHORD programme fits with the Council’s Corporate Plan, Single Outcome Agreement and approved Development Plan policy for town centre regeneration. The economic outcomes from these projects will contribute to the Government’s Economic Strategy. FINANCIAL The Council has made available the sums requested to progress each of the CHORD projects to Full Business Case and for the implementation of Rothesay THI has made £500,000 (five hundred thousand pounds) available. PERSONNEL The resources have been allocated to progress the CHORD Programme. Rothesay THI therefore has funds in place to support an additional post to assist with the financial and administrative areas of the project. EQUAL Each CHORD project will be required to comply with Equal Opportunities. OPPORTUNITIES LEGAL Each of the CHORD projects will require differing levels of legal resources to ensure their timely delivery. Resources have been allocated within each project.
Robert Pollock, Development and Infrastructure Services, Head of Economic Development 09 May 2011
For further information - please contact Nicola Debnam, CHORD Programme Manager Development and Infrastructure Services 01546 604190
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Appointment of chair of new organisationDecision The Board agreed to offer the post of Chair of the new Charity Board to the candidate recommended by the int...
Rothesay Pavilion - Governance StrategyDecision The Board agreed:- To note the information provided and agreed that the Scottish Charitable Incorporated Org...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.