Resolved
Decision The Board noted the information provided. (Reference: Report by the Project Manager dated 11 th March 2013 – submitted)
Rothesay CHORD Project Board noted this item on Wednesday 20 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Board noted the information provided. (Reference: Report by the Project Manager dated 11 th March 2013 – submitted)
HIGHLIGHT / PROGRESS REPORT JANE ROBERTSON (The PROJECT NAME: ROTHESAY PAVILION Project Manager: Prince’s Regeneration Trust) Reporting Period: 21/11/12 – 20/03/13 Date report prepared: 11/03/13 Project stage: HLF Project Development Stage Project stage completion date: March 2014
Tolerance levels for this stage: Project Plan + / - 15 working days Project budget + / - 10%, or £10,000 whichever is greater
Progress – please refer to Project Plan Key products completed this period Key products outstanding this period Revised Key products for next reporting Delivery (including those completed ahead of (including brief explanation of why product delivery date period date schedule) outstanding) HLF Development Grant confirmed - New application to Creative May 13 £103,100 Scotland once Creative Strategy developed HLF Permission to Start received 27/02/13 Procurement of Consultants April/May 13 Formation of new Pavilion Charity Sept 13 Review of design scheme May-Oct 13 Submission of Planning & Listed Oct 13 Building Consents Review of Business Plan Oct 13
Risk Management – please refer to Risk Register Risk Ref. Risk Current status Previous Revised RAG status RAG status RY02_R006 Failure to identify viable scheme Funding, programme and business case all being 8 12 developed
Budget Management – please refer to Resource Allocation Schedule Total budget available to complete this stage: £377,108 Forecast expenditure for current financial year Total expenditure this year (12/13) Variance explanation if required: £21,723 £20,808 (PRT fees)
Previous year’s expenditure Total expenditure to date £227,467 £248,275
1 Any further information Programme - Key Milestones:
1. Capital Fundraising Strategy implemented – applications submitted May – Dec 2013 2. Tender and appoint Consultants – Activity Planning April 2013 3. Submission of Planning & Listed Building Consent applications Oct 2013 4. Completion and submission of HLF Stage 2 application Feb 2014 5. HLF Stage 2 funding outcome July 2014 6. Further development – Design Team & Contractor procurement Summer 2014 – Summer 2015 to European procurement standards 7. Construction Summer 2015 - end 2016 8. Pavilion re-opening Dec 2016
Development Funding secured: Argyll & Bute Council – CHORD Programme £47,000 HLF Development Grant £103,100 HIE £21,500 Total £171,600
Additional development funding for community engagement secured HIE £9,500
Capital Funding requirement: Historic Scotland Building Repair Grant: £500,000 - confirmed Argyll & Bute Council - CHORD Programme £1,853,000 - confirmed Other Capital Grants £885,000 – to be applied for Charitable Trusts & Foundations £900,000 – to be applied for Public Appeal / Gift Aid £25,000 – to be raised HLF Delivery Grant £2,633,397 – confirmation at Round 2 Total £6,796,397
Key points to note:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Rothesay Pavilion: Highlight/Progress ReportReport | 74 KB | DownloadRead as text |
Follow Rothesay CHORD Project Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2014 | Appointment of chair of new organisationDecision The Board agreed to offer the post of Chair of the new Charity Board to the candidate recommended by the int... | Agreed | Open |
| 20 Mar 2013 | Rothesay Pavilion - Project Programme UpdateDecision The Board noted the information provided. (Reference: Report by the Project Manager dated 14 th March 2013 –... | Noted | Open |
| 20 Mar 2013 | Rothesay Pavilion - Governance StrategyDecision The Board agreed:- To note the information provided and agreed that the Scottish Charitable Incorporated Org... | Agreed | Open |
| 20 Mar 2013 | Creative Community Steering Group - Public Open Evening Wednesday 20th March & HI Arts Events Thursday 21st MarchDecision The Board noted the information provided. | Noted | Open |
| 20 Mar 2013 | Apple Tree NurseryDecision The Board agreed that no decisions should be made in regards to this enquiry until such time as the new Pavi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.