Resolved
Decision The Board noted the information provided. (Reference: Report by the Project Manager dated 14 th March 2013 – submitted)
Rothesay CHORD Project Board noted this item on Wednesday 20 March 2013. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Board noted the information provided. (Reference: Report by the Project Manager dated 14 th March 2013 – submitted)
ROTHESAY PAVILION - PROJECT PROGRAMME HLF Development Stage HLF Delivery Stage Compl Task Start Date Date 2013 2014 2015 2016 2017 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Jul-13 Aug-13 Sep-13 Oct-13 Nov-13 Dec-13 Jan-14 Feb-14 Mar-14 Apr-14 Jun-14 Jul-14 Aug-14 Sep-14 Oct-14 Nov-14 Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17
Governance Design Project proposals A&BC Investment Decision - at least 50% Capital funding identified Strategy Scheme prior incl business plan Design Scheme to Planning prior to HLF Rnd2 submission CHORD Board Meetings Design Scheme Communications / Community Engagement
Fundraising
Creative Community Steering Group (CCSG)
Creative Strategy - for Creative Scotland funding application Hi~Arts Hit Team Creative Community Event 21.02.13 22.02.13 Hi~Arts Craft Event Apr-13 Draft Creative Strategy to CHORD Board end April 13 Creative Scotland Capital Grants Application May-13 Hi~Arts Case Studies Event May-13
Governance Strategy
Formation of new Charity
Development of Lease Agreement for long-lease of Pavilion Aug-13 Dec-13
Council engagement with existing Pavilion staff
Design Team - completion of RIBA Stage D Planning & Listed Building Consent notifications Oct-13 Planning & Listed Building Consent submissions Feb-14
Tender & Appoint Other Consultants
Heritage Interpretation Consultant - Research & Storyline Development
Education, Training & Activity Plan Consultant
Market Research, Audience Development & Events Program Consultant
Business Plan re-assessment
Carbon Footprint Assessment
HLF Round 2 Application preparation Submission of application Mar-14 HLF Scottish Committee Jun-14 HLF Board Meeting Jul-14 Round 2 Application deadline - 20 Nov 2014 20.11.14
A&BC Investment Decision - 100% Capital funding in place Jul-14
OJEU/OCG Design Team & Project Manager Tender Action
RIBA Stage E - Technical Design
RIBA Stage F - Production Information
RIBA Stage G - Tender Documentation
OJEU/OCG Main Contractor Tender Action
A&BC Investment Decision - based on tenders
Construction Phase - 18 months
Opening Soft Opening Official Opening Mar-17 Events/Activities commence Mar-17
14/03/2013 1
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Rothesay Pavilion: Project Programme UpdateReport | 146 KB | DownloadRead as text |
Follow Rothesay CHORD Project Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jan 2014 | Appointment of chair of new organisationDecision The Board agreed to offer the post of Chair of the new Charity Board to the candidate recommended by the int... | Agreed | Open |
| 20 Mar 2013 | Rothesay Pavilion - Highlight/Progress ReportDecision The Board noted the information provided. (Reference: Report by the Project Manager dated 11 th March 2013 –... | Noted | Open |
| 20 Mar 2013 | Rothesay Pavilion - Governance StrategyDecision The Board agreed:- To note the information provided and agreed that the Scottish Charitable Incorporated Org... | Agreed | Open |
| 20 Mar 2013 | Creative Community Steering Group - Public Open Evening Wednesday 20th March & HI Arts Events Thursday 21st MarchDecision The Board noted the information provided. | Noted | Open |
| 20 Mar 2013 | Apple Tree NurseryDecision The Board agreed that no decisions should be made in regards to this enquiry until such time as the new Pavi... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.