Resolved
Decision Noted the contents of the report. (Reference: Report by Asset Manager (Amenities), Network and Environment Unit, tabled)
Economy Policy and Performance Group noted this item on Wednesday 25 May 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the contents of the report. (Reference: Report by Asset Manager (Amenities), Network and Environment Unit, tabled)
1.1At the end of 2009 Argyll and Bute Council secured funding from the Scottish Government and LEADER to enable regeneration projects to be taken forward in Dunoon and Bowmore.
2.1Members are asked to note the content of this report concerning the status of each project.
3. DETAILS
3.1In November 2009 the Scottish Government awarded £300,000 to each of Dunoon and Bowmore town centres, to create town centre improvement works (mainly streetscape related improvements) in efforts to assist local economies.
3.2This was part of a national programme in which numerous towns benefited from the Scottish Government Town Centre Regeneration Fund.
3.3Additional contributions provided by the council, LEADER and local community organisations increased the project budgets to £576,227 for Dunoon and £619,900 for Bowmore.
3.4Contract specifications were detailed early in 2010 and contracts were awarded by 31st March, with work commencing June 2010. Main contractors selected were Dunoon - Mackenzie Construction Ltd, Glasgow, and Bowmore - TAL Civil engineering Ltd, Lisburn Northern Ireland.
3.5Both companies used local specialist subcontractors during each of the contracts to supplement their own staff teams.
3.6Contract works in Dunoon are now largely complete, with almost all snagging items having been addressed. There remains an issue of decorative lighting yet to be installed in Castle Gardens outside the Queens Hall and a completion date for this is awaited.
3.7Contract works in Bowmore are complete. 3.8 Costs have been contained within budget limits.
3.9A final claim to draw down European LEADER funding is being prepared, as is a final summary report to the Scottish Government.
4. IMPLICATIONS
4.1Policy: None
4.2Financial : None
4.3Personnel: None
4.4Equalities Impact Assessment: None
4.5Legal: None
For further information, please contact:
Iain Welsh, Asset Manager (Amenities), Network & Environment Unit 01631 569180
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PROGRESS REPORT ON TOWN CENTRE REGENERATION FUNDReport | 51 KB | DownloadRead as text |
Follow Economy Policy and Performance Group at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Feb 2012 | Economic development action planDecision 1. Noted the contents of the report. 2. Noted that the Argyll wide drop out rates were lower, however, bette... | Noted | Open |
| 29 Feb 2012 | Business gatewayDecision 1. Noted the contents of the report. 2. Agreed that a report should be brought to the next meeting in regard... | Noted | Open |
| 29 Feb 2012 | Road equivalent tariff (ret)Decision 1. Noted the contents of the report. 2. It was agreed that the Strategic Transportation Manager would provid... | Noted | Open |
| 29 Feb 2012 | Cowal transport forumDecision Noted the contents of the report. (Reference: Report by Area Governance Officer, dated 28 February 2012, sub... | Noted | Open |
| 29 Feb 2012 | Performance managementDecision 1. Noted the contents of the scorecard. 2. Agreed that the Economic Development Manager and the Performance ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.