Resolved
The Board agreed to note the report. (Ref: A report by Audrey Martin, dated 6 April 2011, submitted).
Campbeltown CHORD Project Board agreed this item on Wednesday 13 April 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
The Board agreed to note the report. (Ref: A report by Audrey Martin, dated 6 April 2011, submitted).
HIGHLIGHT / PROGRESS REPORT PROJECT NAME: CAMPBELTOWN THI Project Manager: AUDREY MARTIN Reporting Period: 10/12/ 2010 – 13/04/2011 Date report prepared: 06/04/2011 Implementation phase (5yrs, 2009- Project stage: Project stage completion date: June 2014 2014)
Tolerance levels for this stage: Project Plan + / - 30 working days Project budget + / - 10%
Key products completed this period Key products outstanding this period Revised Key products for next reporting Delivery (including those completed ahead of schedule) (including brief explanation of why product delivery period date outstanding) date
HLF Quarterly Progress Report approved. Approval of next quarterly progress April 2011 report to HLF Five training events : graphic design creating leaflets Approval of THI grant for old school Dependent illustration on access marketing funding and web site design and VAT issue THI grant for old school submitted
Grant offered on 5 buildings – total grant value £16,100.83 (shop fronts and windows)
Work almost 27-31 Main Street phase 2 (new windows installed)
60 Main Street work almost completed. (roof and windows completed)
Worked stared on Royal Hotel (internal).
d:\moderngov\data\published\intranet\c00000433\m00004608\ai00058670\cn01highlightprogrepapril110.doc Risk Management – please refer to Risk Register Risk Ref. Risk Current status Previous Revised RAG status RAG status Increased cost of original estimated works to Detailed costings are much higher on a number of target buildings 8 12 building due to deteriorating condition and than originally estimated and this may well mean that we cannot resulting short fall in grant funding achieve all our outputs. Looking at viability and deliverability of individual projects. Identification of a public realm scheme and Draft proposals have been prepared and are currently being 8 12 match funding to allow us to utilise £100,000 reviewed with a view to identifying potential match funding ring-fenced in THI bid however if a viable proposal does not come forward in the short term then will consider re profiling and utilising the money allocated for another purpose Shortfall in common fund due to reprofiling of Looking to reprofile costs again and to identify other funding 12 16 costs options to meet shortfall. This process is ongoing and is dependent on projects coming forward which are viable and deliverable.
Budget Management – please refer to Resource Allocation Schedule Total budget available to complete this stage: £1,664,071.00 Forecast expenditure for current financial year Actual expenditure to date Variance explanation if required: £ £ £106,232.95 (31.03.2011)
Any further information
Town hall – continuing to work with SKDT and Campbeltown Community Council (CCC) to secure funding for a development officer to allow then to develop the project to the point of delivery. There is the risk that funding will not be secured for a development officer and or that the timeframes will slip to an extent that the ERDF and THI grant monies will no longer be available. David Rennie from our Social Enterprise team has been identified as the key contact/support officer for SKDT and CCC and we will do everything we can to assist them in taking this forward.
Old School – there is an issue relative to securing the £12,000 contribution towards the access as the Section 75 agreement has not yet been signed and the monies cannot be realised until such time as the agreement is signed. There will be serious implications for the project if this matter is not progressed. The issue of VAT is also an outstanding matter.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
HIGHLIGHT PROGRESS REPORT: CAMPBELTOWN THIReport | 59 KB | DownloadRead as text |
Follow Campbeltown CHORD Project Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Mar 2013 | Kinloch road regeneration public realm - position statement (agenda item 4)Decision Members agreed to note the report and asked that clarification be provided by email to Members by the CHORD ... | Agreed | Open |
| 7 Mar 2013 | Campbeltown budget position statement (agenda item 5)Decision Members agreed to note the report. (Reference: Report by Head of Economic Development and Strategic Transpor... | Agreed | Open |
| 7 Mar 2013 | Campbeltown berthing facility - highlight / progress report (agenda item 6)Decision Members agreed 1. To note the report. 2. That a proper plan needs to be developed to improve the fishermen’s... | Agreed | Open |
| 13 Apr 2011 | Highlight progress report - kinloch road regenerationThe Board agreed to note the report. (Ref: A report by Joanne Casey, dated 4 April, 2011, submitted). | Agreed | Open |
| 13 Apr 2011 | Kinloch road regeneration - update on the impact of extending the public realm scope to incorporate hall streetDecision The Motion was carried by 3 votes to 2 and the Board resolved accordingly. The Chair said that it would be a... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.