Decision 1. Noted the update on the progress of the project. 2. Noted the clarification that there are no formal linkages with the Helensburgh Pier developments and the CHORD project as they are two very separate initiatives. 3. Agreed that the Design Team link in to the H&L LACPG Community Seminar on the 22 May 2010.
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Argyll + Bute Council / Austin-Smith:Lord LLP Helensburgh CHORD Projects 10-03-15 Helensburgh Programme Town Centre Rev E ID Task Name Duration Start Finish Predecessors 2010 2011 2012 2013 201 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J 1 LI STAGE A-B 32 days Mon 14/12/09 Fri 05/02/10 2 Design Team Review of Existing Studies, Designs etc 32 days Mon 14/12/09 Fri 05/02/10 3 Project Inception Meeting 0 days Tue 15/12/09 Tue 15/12/09 15/12 4 Site / Townscape Analysis 32 days Mon 14/12/09 Fri 05/02/10 5 Prepare draft Community Consultation Strategy 13 days Wed 06/01/10 Fri 22/01/10 6 7 LI STAGE C 103 days Mon 25/01/10 Tue 15/06/10 8 Project Board Meeting 01 0 days Mon 25/01/10 Mon 25/01/10 25/01 9 Sign Off Community Consultation Strategy 0 days Fri 05/02/10 Fri 05/02/10 8,5 05/02 10 Meet Economic Consultant and Coordiate Scope of Work 5 days Mon 08/02/10 Fri 12/02/10 5 11 Development of Stage C (Conceptual Designs) 55 days Wed 31/03/10 Tue 15/06/10 2 12 Ongoing Key Stakeholder Consultation 55 days Wed 17/03/10 Mon 31/05/10 2 13 Community Engagement Plan Launch 0 days Fri 26/02/10 Fri 26/02/10 26/02 14 Community / Stakeholder Engagement (Listening Phase) 4.2 wks Fri 26/02/10 Fri 26/03/10 13 15 Topo survey undertaken 28 days Thu 04/03/10 Fri 09/04/10 16 Consultation workshops- Listening 2 days Mon 08/03/10 Tue 09/03/10 17 Ekos business surveys 1 day Tue 23/03/10 Tue 23/03/10 18 Ekos resident surveys returned + baseline survey report complete 1 day Fri 26/03/10 Fri 26/03/10 19 Gazebo day 01 and future walk 1 day Sat 27/03/10 Sat 27/03/10 18 20 Community / Stakeholder Engagement (Options Review Phase) 5.2 wks Mon 29/03/10 Mon 03/05/10 14,19 21 Finalise Presentation Material for Consultation Events 10 days Tue 30/03/10 Mon 12/04/10 22 Complete and procure radar and SI surveys 43 days Wed 31/03/10 Fri 28/05/10 23 Consultation workshops - options 2 days Mon 12/04/10 Tue 13/04/10 24 Ekos monitoring framework report complete 1 day Fri 30/04/10 Fri 30/04/10 23 25 Gazebo day 02 1 day Mon 03/05/10 Mon 03/05/10 24 26 Design Team Feedback to define Preferred Design Option 4 days Tue 04/05/10 Fri 07/05/10 25 27 QS Cost check of preferred design option 10 days Mon 10/05/10 Fri 21/05/10 28 Pre-Application discussions with ABC re Preferred Design Option 10 days Mon 10/05/10 Fri 21/05/10 26 29 Finalise Stage C Design Report (with Costs) 10 days Mon 10/05/10 Fri 21/05/10 26 30 Ekos on street perception survey 1 day Mon 31/05/10 Mon 31/05/10 31 Board Approval to proceed with Preferred Design Scenarios (Stage C) 5 days Wed 09/06/10 Tue 15/06/10 29
32 LI STAGE D + E and Consents 377 days Wed 16/06/10 Tue 06/12/11
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Helensburgh Chord Risk RegisterDecision Noted the update on the current progress of Risk Register. (Ref: Report by CHORD Project Manager, dated 1 Fe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.