Decision Members agreed 1. To note the report. 2. That a proper plan needs to be developed to improve the fishermen’s facilities at Fish Quay to an agreed high and robust standard 3. That full consultation is facilitated with representatives from the Clyde Fisherman Association in regards the improved facilities. 4. That a plan detailing the proposed facilities be submitted to a future MAKI Area Committee for consideration and approval. Further discussion ensued in regards the next meeting date and the need to determine outstanding elements of the Campbeltown CHORD programme.The Area Governance Manager advised that it would be prudent for the Board to review the original Outline Business Case and the Yellow Book Study and to consider the up to date position in regards delivering the totality of the Campbeltown CHORD Project, to ascertain which projects had been delivered, areas for review and to determine unallocated funding. The Board agreed that the next meeting would take the format of a workshop as a means of determining potential options for continuing to progress the overall Campbeltown CHORD. The CHORD Programme manager detailed changes within the CHORD Programme office and it was agreed that she would liaise directly with the Chair and Vice-Chair to decide on the scope of the workshops. A meeting date was agreed for Wednesday 1 May, 2013 at the conclusion of the MAKI Business Day. (Reference: Report by Head of Economic Development and Strategic Transportation, dated 27 February 2013, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Risk Ref. Risk Description Current Status Previous RAG Revised RAG Status Status CN02_R003 Existing marina owned by 3rd party. Transfer of Continued and positive discussion with CLBC 16 8 ownership or lease agreement may be required. CN02_R007 Old quay in danger of collapse or closure – threat Dredging complete and surveys shows no issues 8 4 to delivery of marina of concern CN02_R009 Development of on shore facilities Options and costings prepared. Viable option 16 8 identified CN02_R010 Project not feasible following completion of FBC Interim report demonstrates a potentially viable 12 8 option CN02_R011 Survey of marina- impact of viability of project and Additional surveys identified as being necessary 4 8 associated costs to complete FBC CN02_R025 Flooding of onshore facilities In flood resilience has been designed into 9 6 facilities
c:\users\mcletchiet\appdata\local\microsoft\windows\temporary internet files\content.outlook\j9tk3o5e\cn02_highlight_prog_rep_march 2013.doc Budget Management – please refer to Resource Allocation Schedule Total budget available to complete this stage:
Forecast expenditure for current financial year 2012/13 Actual Expenditure To Date Variance explanation if required £125,000 £14,000 Remainder of budget accounted for to complete FBC.
Any further information
Update Further to the last board meeting, consultants were procured to develop the Full Business Case. The consultant’s primary initial priority was to further develop the new layout proposal submitted by Campbeltown Loch Berthing Company (CLBC); this option has been identified as option D. As option D was developed, the consultants considered there was merit in developing a further option which is a variation on option D; this latest proposal is identified as option E. The three options were presented during an open day/ public workshop in Campbeltown Town Hall in December 2012 which was attended by 36 persons.
The consultants have now completed the development of the three options plus options in respect of onshore facilities and an options appraisal in the form of an interim report is submitted for the consideration of the board. A separate paper is attached with further details and recommendation.
Dredging; board members will recall a proposal to undertake a ‘spend and save’ option of utilising the dredging contractor undertaking work for the New Quay in Campbeltown and the board’s agreement to proceed with this. The dredging has now been completed to a satisfactory manner and in respect of the 3 options above, no further dredging is required.
Next Step The next step is to select the final option (A, D or E) for the finalisation of the Full Business Case, namely full design, up to date costings, secure all the necessary consents and identify management arrangements. This will include additional site investigations to allow the full technical details to be specified.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.