Resolved
Decision Noted the contents of the report. (Reference: Report by CHORD Programme Manager dated 16 December 2011, submitted)
CHORD Programme Management Board noted this item on Friday 13 January 2012. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision Noted the contents of the report. (Reference: Report by CHORD Programme Manager dated 16 December 2011, submitted)
HIGHLIGHT / PROGRESS REPORT PROGRAMME NAME: CHORD Programme Manager: NICOLA DEBNAM Reporting Period: June – December 2011 Date report prepared: 16/12/11
Progress – please refer to Programme Plan Key products completed this period Key products outstanding this period Revised Key products for next reporting period Delivery (including those completed ahead of schedule) (including brief explanation of why delivery date date product outstanding) Helensburgh FBC approved Campbeltown Berthing Facility - FBC September 2012 KRR - Land transfer with ACHA finalised and work Rothesay Pavilion –funding January underway on housing development at Park Square applications to HLF/HS 2012 Campbeltown Berthing Facility – further study Oban FBC February completed 2012 Rothesay THI – first round of applications submitted Dunoon FBC March 2012 December 2011 2 community consultation events held in Oban Helensburgh – appointment of February Contractor 2012 2 community consultation events held in Dunoon 1 community consultation event held in Campbeltown
Risk Management – please refer to Risk Register within Programme Plan Risk Ref. Risk Current status Previous Revised RAG RAG status status PP01_R001 Sufficient external funding cannot be levered in to Continue to monitor and work in partnership with 16 16 complete the programme. funding partners. PP01_R002 That the financial regime for Local Authorities remains Continue to monitor overall funding levels for the 16 16 sufficiently stable to deliver the programme. Council. PP01_R007 Reputational risk to the Council in the delivery of the Continue to ensure that communications strategies are 12 12 Programme. deployed. PP01_R009 That the political environment remains sufficiently stable Continue to ensure that communications strategies are 12 12 to deliver the programme deployed.
d:\moderngov\data\published\intranet\c00000416\m00004940\ai00063605\pp01highlightprogrepjan12v010.doc Budget Management – please refer to CHORD Resources Management Total resource available April ‘11 – Mar ‘12 £4,635,530 (capital and revenue) Forecast expenditure in 2009/10 Actual expenditure for 2009/10 Variance explanation if required: £ £ n/a 824,500 398,499 Forecast expenditure for 2010/11 Actual expenditure for 2010/11 Variance explanation if required: £ £ n/a 1,704,000 1,369,314 Forecast expenditure in 2011/12 Actual expenditure to date 2011/12 Variance explanation if required: £ £ n/a 2,320,530 720,638
Any further information:
Target timescales update: PID approved FBC complete Implementation Completion date Campbeltown THI n/a April ‘09 September ‘09 September ‘14 Berthing Facility June ‘09 September ‘12 unknown unknown Kinloch Road Regeneration June ‘09 April ‘10 November ‘10 December ‘12 Helensburgh Town Centre and West Bay June ‘09 September ‘11 January ‘12 January ‘13 Oban Bay / Harbour April ‘11 December ‘11 Dependent on FBC outcome Rothesay THI June ‘09 May ‘10 April ‘11 April ‘16 Pavilion June ‘09 March ‘11 September ‘13 December ‘14 Dunoon Waterfront June ‘10 February ‘12 January ‘13 September ‘14 (anticipated dates shown in bold)
Programme Plan update:
• 50 % of FBC complete by - March 2011 (achieved) • 100% of FBC complete by – September 2012 (C’town Berthing Facility – delay incurred re: SailWest project) • 50% of projects complete by – September 2014 (C’town Berthing Facility and Oban – dates to be determined) • 100% of projects complete by – April 2016 (C’town Berthing Facility and Oban – dates to be determined) (anticipated dates shown in bold)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CHORD PROGRAMME HIGHLIGHT/PROGRESS REPORTReport | 70 KB | DownloadRead as text |
Follow CHORD Programme Management Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Mar 2013 | Chord programme update - highlight / progress reportDecision The CHORD Programme Board – 1. Noted the report. 2. Agreed that a brief paper containing the detail that had... | Noted | Open |
| 5 Mar 2013 | Chord consultancy frameworkDecision The CHORD Programme Board noted the verbal update. (Reference: Verbal update by CHORD Programme Manager) | Noted | Open |
| 5 Mar 2013 | Lorn arc updateDecision The CHORD Programme Management Board noted the information provided in the presentation. (Reference: Present... | Noted | Open |
| 5 Mar 2013 | Strategic programme board - discussion paperDecision The CHORD Programme Management Board – 1. Agreed to recommend the proposed formation of a Strategic Programm... | Agreed | Open |
| 13 Feb 2012 | LORN ARCDecision Noted the updated position. (Reference: Verbal report by CHORD Programme Manager) E1 | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.