CHORD PROGRAMME GOVERNANCE AND MANAGEMENT ARRANGEMENTS
AgreedCommittee4 papers
Mid Argyll, Kintyre & the Islands Area Committee agreed this item on Wednesday 8 April 2009. Below is the council's own wording, with the papers it was decided on.
Decision 1. The Committee agreed to the recommendations in the report. 2. The Committee agreed to appoint the three Elected Members of Ward 1 to the Project Board. 3. The Committee agreed to appoint Councillor Anne Horn as a non-core consultative member of the Project Board. (Ref: Report by Director of Corporate Services, dated 24 March 2009, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Mid Argyll, Kintyre & the Islands Area Committee
Summary
1.1When the Council decided on 27 November 2008 to allocate, but not yet commit, £30+m of capital funding to projects across Argyll and Bute which followed its consideration of the CHORD OBCs, it remitted to the Executive to establish programme governance arrangements to ensure the CHORD Programme was taken forward in a planned, transparent and accountable way. This involved setting up a Programme Management Board (PMB) to manage the programme and Project Boards to develop and manage the individual projects, following Prince2 and Managing Successful Programmes (MSP) principles.
1.2The attached minute extract is from the PMB meeting on 20 March 2007(Appendix 1). The PMB has agreed Programme Governance and Management arrangements (Appendix 2) and a template for a Project Initiation document (PID) (Appendix 3). The PID is the preliminary deliverable towards the first main deliverable of a Full Business Case (FBC) for each project.
Recommendations
2.1Area Committees and Project Boards are asked to note the Programme Governance and Management arrangements which will be used during the CHORD programme.
2.2Area Committees are invited to appoint relevant local Councillors to be core members of the relevant Project Board
2.3Project Boards are requested to put in place arrangements that will enable them to sign off the completed PID as the first preliminary deliverable of the project.
2.4Project Boards are requested to consider whether they wish to include other people to become non- core consultative members on the Project Board.
3 Detail
3.1The Governance arrangements provide for a Project Board to cover all the projects in each town. This is to comprise the relevant local councillors and the link Director, as core members. It will be those core members of the
Created by Neevia Document Converter trial version http://www.neevia.com Created by Neevia Document Converter trial version Board who sign off the important documents and stages of the project, such as the PID and FBC. Area Committees are asked to appoint the Councillor Members of the Board. The PMB has suggested this should be a small number of local Councillors, appropriate and necessary to the projects being taken forward. Other councillors could be appointed as non–core members where there is a relevant interest. The Board may also include other people from the community eg local community council or others. It should not include any person who may have or represent an organisation which would have a financial interest in any project.
3.2The Programme and Project Management arrangements provide for a Programme Senior Responsible Officer (SRO). This will be the Head of Economic Development and Strategic Transportation who will have ultimate accountability for the delivery of the programme. There will be a Programme Manager, yet to be appointed, by way of secondment for 6 months in the first instance. The recruitment of this person is underway. Each Project will have a Project Manager who will be appointed from within Development Services to lead a Project Team for each project and work with the Project Board. The respective roles associated with all these arrangements are set out in the Programme Governance and Management Arrangements. Area Corporate Services Managers will administer the Project Boards.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Mid Argyll, Kintyre & the Islands Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Supporting communities fund 2026/27Decision The Mid Argyll, Kintyre and the Islands Area Committee agreed that the 21 applications, marked as ‘Award’ an...
Roads and infrastructure services updateDecision The Mid Argyll, Kintyre and the Islands Area Committee noted the contents of the report. (Reference: Report ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.