Decision Noted the contents of the report and that the key products for the next reporting period would be the Benefits Realisation Plan and the Oban Bay/Harbour revised proposal. (Reference: Report by Head of Economic Development dated 7 May 2010, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
HIGHLIGHT / PROGRESS REPORT PROGRAMME NAME: CHORD Programme Manager: NICOLA DEBNAM Reporting Period: January 2010 – May 2010 Date report prepared: 07/05/10
Progress – please refer to Programme Plan Key products completed this period Key products outstanding this period Revised Key products for next reporting Delivery (including those completed ahead of schedule) (including brief explanation of why product delivery period date outstanding) date Draft Campbeltown Kinloch Road Campbeltown Marina Technical and Sep. ‘10 Benefits Realisation Plan Aug. ‘10 Regeneration FBC Feasibility Study – delayed due to funding award from Sailwest INTERREG Draft Rothesay THI Stage Two bid to HLF Oban Bay / Harbour – revised June ‘10 proposal Framework consultants for the Programme appointed
Risk Management – please refer to Risk Register within Programme Plan Risk Ref. Risk Current status Previous Revised RAG status RAG status NO CHANGE TO RISK REGISTER FOR THE PROGRAMME IN THIS REPORTING PERIOD
Budget Management – please refer to CHORD Resources Management Total resource available June ‘09 – Mar ‘10 £824, 500 (capital and revenue) Actual expenditure in 09/10 * Forecast expenditure for 09/10 Variance explanation if required: £ £ x Delays in the appointment of external 398,499 824,500 Project Managers x Delays in the confirmation of external funding
(* see enclosed breakdown of expenditure per town – please note that CHORD expenditure for Oban Development Road does not begin until April 2011.)
o:\f_chord_programme_office\programme_man_board_papers\18_05_10\pp01_highlight_prog_rep_may10_v1.0.doc Any further information
Target timescales update: PID approved FBC complete Implementation Completion date Campbeltown THI n/a April ‘09 September ‘09 September ‘14 Marina June ‘09 unknown unknown unknown Kinloch Road June ‘09 April ‘10 October ‘09 December ‘11 Regeneration Helensburgh Town Centre June ‘09 October ‘11 August ‘12 October ‘13 West Bay June ‘09 January ‘11 November ‘11 January ‘13 Oban Bay / Harbour July ‘09 December ‘09 unknown unknown Dev. Road June ‘09 November ‘13 August’ 14 January ‘16 Rothesay THI June ‘09 May ‘09 October ‘10 October ‘15 Pavilion June ‘09 Feb ‘11 September ‘12 May ‘14 Dunoon Waterfront May ‘10 unknown unknown unknown (anticipated dates shown in bold)
Programme Plan update: 2009 2010 2011 2012 2013 2014 2015 2016 PIDs July approved* 50% of FBC July - delay January complete 100% of FBC Nov complete 50% of June - delay projects September complete 100% of projects January complete (* - Dunoon Waterfront PID for FBC stage – approval anticipated, May 2010) Campbeltown Projects 09/10 Budget-Actual comparison
45,000.00
Campbeltown Town Centre Manager 7,701.83 Total Approved 15000 Funds up to & including 2011/12
100,000.00 Actual Spend 09/10 Campbeltown Kinloch Road 31,486.75
Follow CHORD Programme Management Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.