Decision The CHORD Programme Board – 1. Noted the report. 2. Agreed that a brief paper containing the detail that had been provided under the target timescales update be submitted to each of the four Area Business Day meetings with a view to keeping Members updated on the progress with the CHORD Programme. (Reference: Report by CHORD Programme Manager dated 24 February 2013, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
HIGHLIGHT / PROGRESS REPORT PROGRAMME NAME: CHORD Programme Manager: Helen Ford Reporting Period: November 2012 – February 2013 Date report prepared: 24/02/13
Progress – please refer to Programme Plan Key products completed this period Key products outstanding this period Revised Key products for next reporting period Delivery (including those completed ahead of schedule) (including brief explanation of why delivery date date product outstanding) Campbeltown THI
13-15 Kirk Street – construction phase Town Hall – SKDT stage1 Big Lottery bid approved June 2012 – ABC 50-52 Main Street – agreement reached with existing supporting SKDT with development Town Hall business case - SKDT May 13 owners re: transfer of title. Agreement reached with of business case and stage 2 bid. developer re: design phase. 50 – 52 Main St – Developer complete Further training and complimentary initiative events initial designs / submit Planning and May 13 delivered. Includes; traditional roofing, surveying and listed building applications digital recording and editing. 13-15 Kirk Street – Construction June 13 Two successful historic shopfront events held
Campbeltown Berthing Facility
Full Business Case – Fairhurst appointed to Final option selection March 2013 complete FBC Full Business Case complete May 2013 Stakeholders workshop held in December
Dredging undertaken late 2012 saving circa £60k+ in mobilisation costs
Campbeltown – Kinloch Road Regeneration
Footway Works now combined with Esplanade Soft Landscaping Works Start Date April 2013 Railing Works and Kinloch Road Resurfacing being completed by Breedon Aggregates and McFadyens. Soft Landscaping Completion May 2013
st Soft Landscaping (Park Area) Tender Issued 1 Feb 2013. Contract Award Date 11 March
o:\f_chord_programme_office\programme_man_board_papers\2013\a_050313\pp01_highlight_hp_050313.doc Helensburgh – Town Centre and West Bay Esplanade
Colquhoun Square - amended planning application approved – October 12 Site start in April, construction to take April 2013 th Tender issued for main CHORD works on 8 approximately 15 months) th January, return 15 February – submissions currently being evaluated, aiming to make award by the end of March. Completion of Enabling works April 2013 Enabling Works (Strathclyde Partnership for Transport funding for 2012/13 (£175,000) upgrade of traffic lights in Sinclair St, new signalised S75 – Shopfronts – Delivery process March/April pedestrian crossing in West King St and upgrade agreed 2013 of existing signalised pedestrian crossing in West Clyde St – Tender awarded , pre-start meeting held th on 7 February, Contractor awaiting delivery of equipment before confirming start date.
Paper proposing shop front enhancement scheme (£140,000 S75 funding) going to H&L Business th Day 12 March
Oban - Lorn Arc Steering Group meetings progressing on an TIF Business Case initially envisaged approximate two weekly basis. for January Committee however Completion of Business Case. April 2013 interaction with the LDP and Budget Lorn Rd / Kirk Rd indicative design completed by process in Jan/Feb had led to the Report to Corporate Improvement Board March 2013 ABC Roads team. Additional input from AECOM on decision to report to the March environment and geotech desk studies complete. Committee. Programme and local Update to CHORD Programme Board March 2013 Outline costing included in the business case. area board to be updated. Paper being prepared for DMT to progress to full Update to OLI Area Committee March 2013 design and CPO. Report to Full Council April 2013 Business case consultation progressed. Economic modelling largely complete and now being refined. Issue Business Case to SFT – sign off Financial modelling underway. Draft text and following Full Council in April project issues being discussed with SFT.
Presentations on progress to SMT and OLI Area Committee undertaken.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow CHORD Programme Management Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.