Decision Members agreed to note the report and asked that clarification be provided by email to Members by the CHORD Project Manager on exactly what piece of Kinloch Road is being resurfaced by the funding provided by the Roads Revenue budget (Reference: Report by Head of Economic Development and Strategic Transportation, dated 27 February 2013, submitted).
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
• £224,068 - Footway and Kerbs • £1,505 – Furniture Installation • £12,365 – Hard Landscaping (Planters) • £21,500 - Street Furniture (including New Road) • £28,000 - Street Lighting • £61,000 - Soft Landscaping (Contractor still to be appointed awaiting tender returns) • £60,000 – Esplanade Railings • £75,000 – Royal Hotel Total £483,438
NON CHORD Funded
• £151,540 – Kinloch Road Resurfacing funded from Renewable’s budget • £75,271 – Kinloch Road Resurfacing funded from Road’s budget • £45,000 – Kinloch Road Drainage funded from Renewable’s budget Total £271,811
Overall Project Cost £755,249
1 3.3 The construction spend to date is approximately £99,000. The overall projected final cost is approximately £780,000.
3.4Projected timescales for completion of the Kinloch Road Regeneration Public Realm Project are as follows:
• Footway & Kerb works – 1st April 2013 • Esplanade Railings – 1st April 2013 • Park Area Soft Landscaping (awaiting tender returns) works due to be completed by the end of April 2013.
Additionally the Non CHORD Kinloch Road Resurfacing are also due for completion by the end of April 2013.
3.5Breakdown of approved budget allocation of £1,250,000 as follows:
• Total £1,250,000 • Projected final CHORD construction costs £485,000 • Projected fees £85,000
Balance £680,000
IMPLICATIONS
POLICY The delivery of the CHORD programme fits with the Council’s Corporate Plan, Single Outcome Agreement and approved Development Plan policy for town centre regeneration. The economic outcomes from these projects will contribute to the Government’s Economic Strategy. FINANCIAL The funding has been allocated to progress the public realm element of the Kinloch Road Project. PERSONNEL The resources have been allocated to progress the CHORD Programme. EQUAL There are no equal opportunities implications. OPPORTUNITIES LEGAL Each of the CHORD projects require differing levels of legal resources to ensure their timely delivery. Resources have been allocated to each project as per the approved Project Initiation Documents.
Robert Pollock Development and Infrastructure Services, Head of Economic Development and Strategic Transportation 27 February 2013
For further information - please contact Helen Ford, CHORD Programme Manager Development and Infrastructure Services, Economic Development and Strategic Transportation 01436 658839
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.