SHORT LIFE WORKING GROUP - ROADS ASSET MANAGEMENT AND MAINTENANCE STRATEGY agreed this item on Monday 11 March 2013. Below is the council's own wording, with the papers it was decided on.
Decision The Short Life Working Group - In terms of roads hierarchy; agreed to recommend to the Council - To adopt the new proposed roads hierarchy, subject to caveats which would provide a degree of flexibility for ongoing review and with the following amendments to the draft as detailed at 3.7 of the report – · Change “Local Plan” to “Local Development Plan” throughout. · Under rank one add the A819 to the list of roads under detailed description. · Under rank 3 consideration to be given by Officers to the replacement of the word lightly with a more appropriate word under detailed description. To instruct Officers to re-categorise the roads in Argyll and Bute into this hierarchy for consideration by the four Area Committees before September 2013. To suspend operation of the Short Life Working Group until such time as the new roads hierarchy has been considered by the four Area Committees and thereafter the Short Life Working Group would take into consideration the new hierarchy and comments by Area Committees with a view to assessing the effects on the budget process and the prioritisation of capital funding for the financial year 2014/15. That a further report be provided to the Council in October 2013. In terms of road defects and response times; noted that this did not entirely fall under the remit of the Short Life Working Group but agreed recommend to the Council - To approve the proposed Category 1 pothole definitions subject to simplification of the language and changes to the chart layout. To approve the maximum response time for category 1 defects being increased to 5 working days to facilitate more economic use of resources and higher quality repairs. That the revised approach should be supported by a publicity strategy. (Reference: Additional reports (2) by Head of Roads and Amenity Services dated 8 March 2013, tabled)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to SHORT LIFE WORKING GROUP - ROADS ASSET MANAGEMENT AND MAINTENANCE STRATEGY
Road Maintenance & Asset Management Plan for the Road Network
February 2004 (Revised November 2005) ROADS MAINTENANCE & ASSET MANAGEMENT PLAN
INDEX
SECTION 1: INTRODUCTION
1.1Purpose of the Plan 1.2 Definitions
SECTION 2: GENERAL
2.1The Importance of Road Maintenance 2.2 Road Maintenance Strategy 2.3 Sustainable Road Maintenance 2.4 Objectives of the Plan 2.5 Managing Complaints 2.6 Legal Framework 2.7 Health & Safety 2.8 Management of Risk
SECTION 3: MAIN ELEMENTS OF THE PLAN
3.1Network Hierarchy 3.2 Network Inventory 3.3 Category of Maintenance 3.4 Training and Development 3.5 Inspection Regime 3.6 Safety Inspections 3.7 Recording of Defects 3.8 Service Inspections 3.9 Methodology of Inspections 3.10 Condition Standards
SECTION 4: MATERIALS AND TREATMENTS
SECTION 5: PROCESSES
5.1Quality Management and Sector Schemes
SECTION 6: DEPOTS AND MATERIALS STORAGE
SECTION 7: STREET LIGHTING SECTION 8: MEASURING PERFORMANCE
A Average Revenue Spend 2001-2004 B Rates for each Maintenance Activity C Calculation of Rates for each Maintenance Activity D Totals for each Activity ROADS MAINTENANCE & ASSET MANAGEMENT PLAN 1 INTRODUCTION 1.1 PURPOSE OF THE PLAN
1.1.1 The main purpose of road maintenance is to ensure that the road network is available for the safe and convenient movement of people and goods. This purpose however needs to be set within the wider contexts of integrated transport, Best Value and the corporate vision of the Council.
1.1.2 The purpose of this plan is to design a sustainable maintenance regime capable of managing the road network asset within the available resources and ensuring that the asset will be available for future generations.
1.1.3 What the Plan does :-
The plan will set condition standards for the various elements of the road network and optimum timescales for the various activities that are undertaken to maintain the condition of the road network. This is achieved by :-
1. Collecting Inventory
By collecting and quantifying the relevant inventory along each length of road (width, length, number of gullies etc., lengths of ditches, walls, footways) the workload required to maintain the road network to the relevant standard can be established and costed.
2. Establishing the Hierarchy of the Roads
The hierarchy or importance of each road link will be used to decide the standard of maintenance to be applied, the regulatory of inspections and the prioritising of the repairs to be undertaken.
3. Setting Standards for the Condition of the Network to be Maintained at
The maintenance plan sets the standards that the road will be maintained at taking into account the relevant factors such as importance of the route, traffic volumes, population served and the available overall budget.
4. Inspecting
Frequency of inspections to identify faults will be set for each route.
5. Prioritising Repairs
The urgency of repairs required will be set and available resources allocated to repairing the most important faults as a priority. 6. Matching workload to available budget
If funds are inadequate the standards of maintenance will be adjusted to balance the workload to match the available budget.
7. Programming Work
The overall workload having been identified will allow the most efficient programme of works to be set for completion during the financial year.
Each year this process will be reviewed and repeated to match the new budget and any increase in costs.
1.2DEFINITIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow SHORT LIFE WORKING GROUP - ROADS ASSET MANAGEMENT AND MAINTENANCE STRATEGY at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads asset life cycle planningDecision The Short Life Working Group noted the demonstration. (Reference: Demonstration by Jamie McLafferty, Technic...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.