Decision The Council noted the capital plan monitoring report and approved the projects to be slipped and the projects to be accelerated as detailed in the submitted report. (Ref: Report by Head of Strategic Finance dated 21 March 2013, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This provides an update on the position with the capital plan as at 31 December 2012. The report provides information on the financial position in respect of the capital plan and also the performance in terms of delivery of capital plan projects.
1.2The position on the capital plan can be summarised as set out below:
1.3Project Delivery:
Asset Sustainability – Out of 203 projects there are 179 projects (88%) on track, 20 projects (10%) off track and recoverable and 4 project (2%) off track. Service Development - Out of 60 projects there are 50 projects (83%) on track, 5 projects (8%) off track but recoverable and 5 projects (8%) off track. Strategic Change – Out of 26 projects there are 9 projects (35%) on track, 10 projects (38%) off track and recoverable and 7 projects (27%) off track.
1.4Financial Position:
Forecast Outturn for 2012-13 – Forecast expenditure for the full financial year is £30,329k compared to an annual budget of £29,635k giving rise to forecast over spend for the year of £694 (2.3%).
Current Year to Date - Actual expenditure to date is £23,977k compared to a budget for the year to date of £23,971k giving rise to an over spend for the year to date of £6k (0.25%).
Total Capital Plan – The forecast total project cost on the total capital plan is £139,146k compared to a total budget for all projects of £136,223k giving rise to a forecast overspend for the overall capital plan of £2,923k (2.1%). 2 RECOMMENDATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Political management arrangementsDecision The Motion was carried by 18 votes to 8 votes, with 2 no votes, and the Council appointed Councillor Jan Bro...
Programme for government 2026 - 2031Decision The Motion was carried by 16 votes to 8 and the Council resolved accordingly. (Reference: Report by Chief Ex...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.