Resolved
Decision 1. Noted and approved the contents of the report; and 2. Noted that the Review of the Council Ledger would now be the end of March 2014. (Reference: Report by Internal Audit dated 17 February 2014, submitted)
Audit Committee noted this item on Friday 14 March 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision 1. Noted and approved the contents of the report; and 2. Noted that the Review of the Council Ledger would now be the end of March 2014. (Reference: Report by Internal Audit dated 17 February 2014, submitted)
1.1Internal Audit document the progress made by departmental management in implementing the recommendations made by both External Audit and Internal Audit. Set out below are the results from a review performed by Internal Audit for recommendations due to be implemented by 31 January 2014.
2.1The contents of this report are noted and approved by the Audit Committee.
3. DETAILS
3.1The process requires departmental Executive Directors assigning a 3rd tier officer to act as the sole contact for the follow up of both external and internal recommendations. The contact role involves updating both the Executive Directors and Internal Audit on progress with agreed audit recommendation implementation.
3.2Appendix 1 is a statistical summary of all agreed recommendations arising from National, External and Internal Audit reports by department. Detailed is the number of recommendations due as at 31 January 2014, the number implemented, the number of agreed future recommendations and their status, e.g. on course etc.
3.3Appendix 2 provides a summary as at 31 January 2014, of all outstanding recommendations from National, External and Internal Audit reports by department and service. Detailed is the report name along with the weakness identified, agreed management action, revised date, any previous implementation dates reported to the Audit Committee management comment and Pyramid status.
3.4Appendix 3 provides a summary of all recommendations from National, External and Internal Audit reports by department and service that are due after 31 January 2014 and not on track to achieve the agreed implementation dates. Detailed is the report name along with the weakness identified, agreed management action, revised date, any previous implementation dates reported to the Audit Committee, management comment and Pyramid status. 4. CONCLUSIONS
Of the 38 recommendations due for completion by 31 January 2014, 18 have been completed. Internal Audit is satisfied that progress is being made in addressing all 20 remaining recommendations and with the revised completion dates provided.
Good progress is being made on the 24 recommendations due after 31 January 2014 with 4 completed early and timely identification of 2 requiring to be rescheduled.
5. IMPLICATIONS
5.1Policy: None
5.2Financial: None
5.3Legal: None
5.4HR: None
5.5Equalities: None
5.6Risk: None
5.7Customer Service: None
For further information please contact Internal Audit on (01546 604294) 17 February 2014
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
EXTERNAL AND INTERNAL AUDIT REPORT FOLLOW UP 2013: 2014Report | 49 KB | DownloadRead as text |
PDF |
Ext and Int appendix 1Appendix | 73 KB | Download |
PDF |
Ext and Int appendix 2Appendix | 70 KB | Download |
PDF |
Ext and Int appendix 3Appendix | 45 KB | Download |
Follow Audit Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Mar 2017 | Internal audit summary of activitiesDecision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... | Noted | Open |
| 24 Mar 2017 | Internal audit reportsDecision The Committee noted the contents of the summary report and the detail within each individual report. (Refere... | Noted | Open |
| 24 Mar 2017 | External & internal audit report follow-up 2016 - 2017Decision The Committee noted the contents of the report. (Reference: Report by Chief Internal Auditor dated 24 March ... | Noted | Open |
| 24 Mar 2017 | Internal audit annual plan 2017 - 2018Decision The Committee agreed and approved the Internal Audit Annual Plan 2017/18 (Reference: Report by Chief Interna... | Agreed | Open |
| 24 Mar 2017 | External audit plan 2017 - 2018Decision The Committee noted the contents of the report. (Reference: Report by Audit Scotland dated March 2017, submi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.