Resolved
Decision The Committee noted the update provided. (Ref: Report by Oban Regeneration Project Manager dated 13 th March 2014, submitted).
Oban Lorn & The Isles Area Committee noted this item on Wednesday 9 April 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the update provided. (Ref: Report by Oban Regeneration Project Manager dated 13 th March 2014, submitted).
1.1Aim of Update
The purpose of this report is to bring the OLI Area Committee up to date with the progress that has been made and actions taken since the last Area Committee.
Separate concept design reports have been submitted for two of the projects – Enhancement of Oban Bay from Stafford Street to Station Square, including George Street; and North Pier Maritime Visitor Facility.
2.0UPDATE 2.1 Public Realm: Further Upgrade of Amenity Lighting at McCaig’s Tower The main project was completed in November 2013 with responsibility for the amenity lighting activity being given to Och Aye Events company on a one year operating agreement and the maintenance and management being handed over to the Council’s Street Scene team ahead of the opening of the Winter Festival on 22nd November, 2013.
There are three components to our lighting scheme: 1) the façade colour changing lighting scheme which is a permanent feature; 2) a trial lighting scheme which washes a sample of the window frames with changing colour light and 3) the facility for the resident and business community to colour code the tower façade in a single colour by arrangement for special events such as Valentine’s Day (red); Sea Festival (blue); Christmas (white); by prior arrangement through Och Aye Events company. This latter service became available during March 2014.
As a result of public feedback and available funding within our budget we have subsequently installed one new pole to allow us to light up the gap at the side of the Tower. We have also been able to add some lighting to the façade at the pedestrian entrance to the Tower in a way which also provides improved visibility for pedestrians.
This capital project is now completed. An in use review and evaluation report will be undertaken in accordance with good practice. Target June 2014.
2.2Public Realm: Enhancement of Oban Bay from Stafford Street to Station Square including George Street The Capita design team have completed the concept design phase following consultations with statutory bodies and consultations with key stakeholders October – February. A separate report and recommendations for moving to detailed design on a preferred option are on the Agenda for this meeting.
Transport Scotland/Capita Design Review: the design teams continue to discuss issues/ constraints and exchange available maintenance and construction programming information.
Target date for approval to move from concept design to detailed design stage (RIBA Stage 3)– 9th April, 2014.
Target date for seeking planning approval from PPSL, if deemed appropriate,– 20th August, 2014.
Target date for securing Detailed design and full business case approval – September 2014.
2.3Public Realm: Provision of Maritime Visitor Facility in North Pier Maritime Quarter (White Building) Oberlanders, the Edinburgh based architects who are a member of our Capita team, have now completed the concept design phase following receipt of building and topographic survey results and early consultations with occupants of the North Pier, Historic Scotland and our planning and roads teams.
A separate report and recommendations for moving to detailed design on a preferred option are on the Agenda for this meeting.
Target date for approval to move from concept design to detailed design stage (RIBA Stage 3)– 9th April, 2014.
Target date for planning application to be determined by PPSL – 20th August.
Target date for securing Detailed design and full business case approval – September 2014.
2.4Oban Bay Breakwater, Step Ashore and Transit Facility Fisher Associates are working for the OBDHG on a study which could impact on design proposals and the successful TIF application impacting on the North Pier creates a changed environment within which the Council can adopt a more holistic economic development approach to the development potential of it’s own asset – the North Pier.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
OBAN CHORD UPDATE STATEMENTReport | 74 KB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.