Resolved
Decision On a show of hands, the motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Ref: Report by Oban Regeneration Project Manager dated 15 th April 2015, submitted).
Oban Lorn & The Isles Area Committee decided this item on Wednesday 15 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision On a show of hands, the motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Ref: Report by Oban Regeneration Project Manager dated 15 th April 2015, submitted).
1.1There are now essentially four phases to the delivery of the Oban North Pier Maritime Quarter. Phase 1 consists of the North Pier Maritime Visitor Facility, for which the Full Business case was approved by Council in September 2014. Following a non- planning legal challenge from an adjacent business a revised planning application has subsequently been lodged and a decision is expected later this month. Phases 2 and 3 addresses the need for interim step ashore solutions for cruise liner passengers and other users for 2015 and 2016, whilst Phase 4 will outline the development process for an Integrated Maritime Quarter Facility, inclusive of a short stay transit berthing/step ashore facility.
1.2The purpose of this report is to:
a) update members on the current position in delivering the Oban North Pier Maritime Quarter;
b) advise members on the outcome of the evaluation of OBM Ltd’s recent Business Plan;
c) seek support to proceed with the interim step ashore solutions for 2015 as outlined in the paper;
d) seek support to recommend to the Policy and Resource Committee the approval to drawdown £45,000 to advance the development stage of the interim step ashore solution for 2016.
1.5It is recommended that the OLI Area Committee:
• Note and endorse the contents of this paper;
1 • Request officers to implement the interim step ashore solution proposals for 2015; • Recommend to the Policy and Resource Committee, for their interest, the drawdown of £45,000 to implement the development stage of the interim step ashore solution for 2016; • Request officers to bring an update report outlining the implementation cost of delivering the 2016 interim step ashore solution following completion of the development stage, which is likely to be around September/October 2015; and • That the Oban CHORD Project Managers brings an update report on the delivery of the Oban North Pier Maritime Quarter to subsequent Area Committee meetings.
2 ARGYLL AND BUTE COUNCIL Oban Lorn and the Isles (OLI) Area Committee
DEVELOPMENT AND INFRASTRUCTURE SERVICES 15th April, 2015
OBAN CHORD - OBAN NORTH PIER MARITIME QUARTER – UPDATE AND REQUEST FOR FUNDING
2.1Aim of Update
To update members on the delivery of the Oban North Pier Maritime Quarter and to seek support to take forward the interim step ashore solution proposals for 2015 and 2016, whilst progressing the development of the Integrated Maritime Quarter Facility.
3.1It is recommended that the OLI Area Committee:
• Note and endorse the contents of this paper; • Request officers to implement the interim step ashore solution proposals for 2015; • Recommend to the Policy and Resource Committee, for their interest, the drawdown of £45,000 to implement the development stage of the interim step ashore solution for 2016; • Request officers to being an update report outlining the implementation cost of delivering the 2016 interim step ashore solution following completion of the development stage, which is likely to be around September/October 2015; and • That the Oban CHORD Project Managers brings an update report on the delivery of the Oban North Pier Maritime Quarter to subsequent Area Committee meetings.
4.0DETAILS
4.1There are essentially now four phases to the delivery of the Oban North Pier Maritime Quarter: 3 • Phase 1 - North Pier Maritime Visitor Facility • Phase 2 – Interim step ashore solution for 2015 • Phase 3 - Interim step ashore solution for 2016 • Phase 4 - Integrated Maritime Quarter Facility, inclusive of a short stay transit berthing/step ashore facility.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
OBAN CHORD: OBAN NORTH PIER MARITIME QUARTER: UPDATE AND REQUEST FOR FUNDINGReport | 94 KB | DownloadRead as text |
PDF |
OBM paper appendix AAppendix | 199 KB | Download |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.