CHORD - OBAN: NORTH PIER HARBOUR BUILDING AND NORTH PIER PONTOONS - PROJECT CLOSURE
NotedCommittee1 paper
Oban Lorn & The Isles Area Committee noted this item on Wednesday 11 March 2020. Below is the council's own wording, with the papers it was decided on.
Decision The Oban, Lorn and the Isles Area Committee; 1. noted and welcomed the report; 2. thanked and congratulated officers on the success of the project; and 3. commended to Council the North Pier Harbour Building and North Pier Pontoons – Project as an example of a well delivered project that has had a positive impact on Oban’s tourism economy. (Reference: Joint Report by Interim Executive Director with responsibility for Development and Economic Growth and Executive Director with responsibility for Commercial Services dated 31 October 2019)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to update Members on the economic outcomes secured following the completion of the North Pier Harbour Building and the North Pier Pontoons in Oban. 1.2 The report provides a summary of the economic outcomes of the investment, actual against those forecast in the Full Business Case, from October 2016. 1.3 The recently commissioned independent review of economic outcomes indicates that the Pontoons and Harbour Building have had an overall positive impact on Oban’s tourism economy and have generally outperformed the original forecasts. The data demonstrates that the Pontoons have been successful in attracting additional maritime vessels and visitor numbers, which have made a substantial contribution to the marine tourism offer in Oban, and indeed to the wider Argyll & Bute area. 1.3 The report also outlines the preferred future management route for the North Pier Pontoons. 1.4 The Oban Lorn and the Isles Area Committee is invited to:
1.4.1 Note and consider the contents of this report. ARGYLL AND BUTE COUNCIL OBAN, LORN AND THE ISLES AREA COMMITTEE
DEVELOPMENT AND ECONOMIC 11 MARCH 2020 GROWTH & COMMERCIAL SERVICES
CHORD – Oban: North Pier Harbour Building and North Pier Pontoons – Project Closure
2.0INTRODUCTION
2.1The revised Full Business Case (FBC) for the Oban North Pier Maritime Quarter – Phase One – Maritime Visitor Facility was approved in October 2016. Following the procurement exercise a principal contractor, TSL was appointed in March 2017. The project achieved practical completion in March 2018 with the first tenant leasing a unit in the building at the end of that same month. The works contract completed in November 2018 and the defects rectification period completed at the end of November 2019, within budget.
2.1.1 The original proposals for the Maritime Visitor Facility were altered due to objections lodged by an adjacent business and concerns as to the overall affordability of the project. The “Gathering Place” design concept was substantially changed to a more functional and compact “wedge” shaped building, which sits within the boundary of the former White Building, and the project was renamed the Oban North Pier Harbour Building.
2.1.2 The Harbour Building includes: dedicated showers, toilets, changing area; and secure storage lockers for maritime visitors. Additionally there are 4 commercial spaces, two on the mezzanine floor and two on the ground level, including: a harbour-master’s office; an office for the North Pier Pontoons operator; and two additional spaces, one let as a shop, and one room available for hourly rentals for meetings and presentations.
2.2The Transit Berthing Facility was renamed the Oban North Pier Pontoons project: in April 2015 the Oban, Lorn and the Isles (OLI) Area Committee approved the design layout and subsequently in June of that year approved the recommendation to seek approval for development funding from the Policy & Resources Committee to enable the project to be taken forward to the procurement stage. A revised CHORD budget allocation of £1.5m, was supplemented by external funding of £700k from RCGF and £300k from HIE, giving a total capital budget of £2.5m. The construction contract was awarded in December 2016 with the facility operational by the end of July 2017. The contract closed out in December 2019, within budget. 3.0 RECOMMENDATIONS
3.1The Oban, Lorn and the Isles Area Committee is invited to:
3.1.1 Note and consider the contents of this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.