Resolved

Decision 1. The Committee agreed to recommend to the Council, to grant funding to the LWW of £10,000 per annum for a three year period commencing April 2016; subject to - a) the completion of a service level agreement with the LWW which requires that the LWW should continue to develop its partnership working with the Argyll & the Isles Coast and Countryside Trust and its Long Distance Routes Forum, b) evidence of financial viability for each year being presented to and approved by the Council before the release of each annual payment and; c) that LWW be advised that this is the final financial support from the Council; to be funded from General Fund Balance. 2. In addition members noted that if the LWW cannot find a sustainable way forward no financial burden would fall upon the Council. Councillor Gary Mulvaney , who had moved an amendment which failed to find a seconder, requested that his dissent be recorded from the foregoing decision. (Reference: Report by Executive Director – Development and Infrastructure Committee dated March 2016, submitted) *
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Policy and Resources Committee

ARGYLL AND BUTE COUNCIL POLICY & RESOURCES COMMITTEE DEVELOPMENT AND INFRASTRUCTURE SERVICES 17 MARCH 2016 LONG AND WINDING WAY – FUNDING REQUEST

1. EXECUTIVE SUMMARY 1.1 In February 2015 the Long and Winding Way Ltd (LWW) which manages the Kintyre Way Long Distance path made an emergency funding request to the Council. 1.2 Following this request the LWW secured emergency funding from a variety of other sources including SNH, Campbeltown Common Good Fund and the Development and Infrastructure Access and Economic Development Budgets. Additional in December 2015, £100,000 from the Coastal Communities Fund was awarded for specific projects, but this must be spent in 2016 and cannot be used for core funding. 1.3 The LWW is making a core funding request to the Council for a three year Service Level Agreement of £60,000 equally split over years 16/17, 17/18, 18/19. 1.4 The Kintyre Way was opened in 2006 but has not yet established viable ongoing funding despite being provided £72,000 by the Council to support its continued development to date. The business plan submitted and appended, articulates its approach to operating the Kintyre Way and their approach to risk. However, the LWW is proposing to gain £85k of funding between 2017/19 from wind farm developments via Section 75 Agreement. There is a risk that this may not be achieved and there would subsequently be an equivalent funding gap in the LWW business plan. This is partly because the wind farms are not certain to be implemented; and also because the Council currently seeks planning gain via voluntary contributions from renewable energy developers instead of S75 agreements, and has an existing commitment to allocate this money to a Trust rather than directly to the LWW or other groups. The LWW could make a bid to this trust but would be competing with other groups. If there are any localised impacts from wind farm developments directly upon the Kintyre Way there may be the opportunity for the negotiation of mitigation of that impact through a S75 agreement, but this could only be determined at the time of such planning applications and directly relating to the identified impact. In any case, should the LWW fail the Council has no responsibility for the maintenance of the Kintyre Way.

2.0RECOMMENDATIONS 2.1 Members note the content of the assessment process and determine whether or not to grant the LWW request for a £60,000, three year funding agreement, which if granted would be agreed with the LWW through a detailed Service Level Agreement. 2.2 Members should consider whether any grant of funding should be;  offered subject to the LWW continuing to develop its partnership working with the Argyll & the Isles Coast and Countryside Trust (ACT) and its Long Distance Routes Forum.  be considered a final grant payment by the Council; and  note that if the LWW cannot find a sustainable way forward no burden would fall upon the Council. ARGYLL AND BUTE COUNCIL POLICY & RESOURCES COMMITTEE DEVELOPMENT AND INFRASTRUCTURE SERVICES 17 MARCH 2016 LONG AND WINDING WAY – FUNDING REQUEST

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LONG AND WINDING WAYReport 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 18 attended
DW
Councillor Dick WalshChair, present
RC
Councillor Rory ColvilleMember, present
RC
Councillor Robin CurrieMember, present
MC
Councillor Maurice CorryMember, present
MD
Councillor Mary-Jean DevonMember, apologies
RM
Councillor Roderick McCuishMember, present
IM
Councillor Iain MacLeanMember, apologies
AM
Councillor Alistair MacDougallMember, present
NM
Councillor Neil MacIntyreMember, present
AM
Councillor Aileen MortonMember, present
EM
Councillor Ellen MortonVice-Chair, apologies
GM
Councillor Gary MulvaneyMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. LONG AND WINDING WAYThis decision
  2. Long and winding way company ltd - appointment of councillor to the boardAgreed

More from Argyll and Bute Policy and Resources Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... Agreed Open
20 Aug 2026 Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... Noted Open
20 Aug 2026 Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... Noted Open
20 Aug 2026 Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... Agreed Open
20 Aug 2026 Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies