Decision The Committee noted – 1. The revenue budget monitoring report as at 31 January 2016. 2. The current assessment of the Council’s financial risks. 3. The overall level of reserves and balances and the monitoring of the earmarked reserves. 4. The capital plan monitoring report as at 31 January 2016. 5. The treasury monitoring report as at 31 January 2016. (Reference: Report by Head of Strategic Finance dated 16 February 2016, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
ARGYLL AND BUTE COUNCIL POLICY AND RESOURCES COMMITTEE
STRATEGIC FINANCE 17 MARCH 2016
EXECUTIVE SUMMARY FINANCIAL REPORT MONITORING PACK – JANUARY 2016
1. INTRODUCTION
1.1This report provides a summary of the financial monitoring reports as at the end of January 2016. There are five detailed reports summarised in this Executive Summary:
Revenue Budget Monitoring Report as at 31 January 2016 Monitoring of Financial Risks Reserves and Balances Capital Plan Monitoring Report as at 31 January 2016 Treasury Monitoring Report as at 31 January 2016
The web link to the detailed reports is as follows: http://www.argyll-bute.gov.uk/financial-monitoring
2. DETAIL
2.1Revenue Budget Monitoring Report
2.1.1 This report provides a summary of the current revenue budget monitoring position to ensure net expenditure is contained within budget. It provides corporate and departmental information with comparisons on a forecast outturn and a year to date basis.
2.1.2 The current forecast outturn position is a projected underspend of £1.036m, of this £0.130m will require to be earmarked at the year-end to fund the Waste Model resulting a reduced forecast underspend of £0.906m. This compares to an underspend reported at 31 December 2015 of £0.739m, an increase in the forecast underspend of £0.167m.
2.1.3 The current underspend includes balances that are non-recurring underspends totalling £1.464m. These specifically include £0.514m for the excess pay award – when the 2015-16 budget was prepared the pay award was estimated at 2%, however, was subsequently settled at 1.5% resulting in an underspend equivalent to 0.5% £0.500m council tax empty homes income £.0450m for loans charges. 2.1.4 The changes from the position reported at 31 December 2015, contributing to the revised underspend as at 31 January 2016, are noted as: Integration: Decrease in the forecasted overspend of £0.144m. This relates mainly to a reduced forecast in demand for homecare and supported living services within Adult Care. In addition, the forecasted expenditure for Central Management and Criminal Justice has reduced. Development and Infrastructure: Decrease to the forecasted overspend of £0.023m. This is mainly due to car parking and DPE income being better than forecast and increased vacancy savings. These are offset by a further reduction in berthing dues at Rothesay Harbour due to maintenance work at Wemyss Bay an increase to the projected overspend in relation to Winter Maintenance.
2.2Monitoring of Financial Risks
2.2.1 This report outlines the process and approach developed in carrying out a financial risks analysis and provides an update on the current assessment of financial risks.
2.2.2 There are a number of Council wide risks identified, none of which have been classed as likely or almost certain. The risk in respect of Auto Enrolment has been classed as possible; however, the majority of staff will not be auto enrolled until 2017 and the estimated worst case financial impact has been built into the medium term budget outlook.
2.2.3 There are currently 62 departmental risks totalling £8.397m. Only 9 of the risks are categorised as likely, with a potential impact of £2.373m, and no risks have been categorised as almost certain. These will continue to be monitored and action taken to mitigate or manage these risks.
2.2.4 The top 3 risks in terms of their likely financial impact are noted in the table below. SERVICE TITLE OF RISK DESCRIPTION OF RISK LIKELIHOOD FINANCIAL IMPACT £000 Adult Care Increased complexity of Level of service demand remains at 3 950 care packages - Older current commitment or increases due People, Physical Disability, to needs becoming more complex. Learning Disability and Mental Health Adult Care Growth in Older People Growth in elderly population exceeds 3 700 population expectation reflected in Demand Pressure thereby putting increased demand on services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-...
Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.