Resolved
Decision The Committee – 1. Noted the details provided. 2. Noted the actions being taken to mitigate the risks described. (Reference: Report by Executive Director – Customer Services dated 3 March 2016, submitted)
Policy and Resources Committee noted this item on Thursday 17 March 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee – 1. Noted the details provided. 2. Noted the actions being taken to mitigate the risks described. (Reference: Report by Executive Director – Customer Services dated 3 March 2016, submitted)
1.1This report updates the Policy & Resources Committee on the Broadband Pathfinder re-procurement for a wide area network for the council providing connectivity to all schools, libraries and offices. It details the progress following the paper presented to the Council meeting on 13 February 2014 which approved the business case and associated costs, and delegated authority to the Executive Director Customer Services to conclude the Minute of Agreement with Highland Council.
1.2It highlights that there has been a six month delay to finalising the order for sites with Capita, and that Capita has served a notice on the partnership claiming relief for delay of up to 6 months. At present their plans for transition show that all our sites should be implemented by end of September 2016 as per the original milestones. However, there is risk of a delay which would bring risks to business continuity and possible additional costs. The paper sets out the actions being taken to mitigate these risks and the Committee is asked to note these. ARGYLL AND BUTE COUNCIL POLICY & RESOURCES COMMITTEE
CUSTOMER SERVICES 17 MARCH 2016
BROADBAND PATHFINDER NORTH UPDATE
2 INTRODUCTION
2.1This report updates the Policy & Resources Committee on the Broadband Pathfinder re-procurement for a wide area network for the council providing connectivity to all schools, libraries and offices. It details the progress following the paper presented to the Council meeting on 13 February 2014 which approved the business case and associated costs, and delegated authority to the Executive Director Customer Services to conclude the Minute of Agreement with Highland Council
2.2It highlights that there has been a six month delay to finalising the order for sites with Capita, and that Capita has served a notice on the partnership claiming relief for delay of up to 6 months. At present their plans for transition show that all our sites should be implemented by end of September 2016 as per the original milestones. However, there is risk of a delay which would bring risks to business continuity and possible additional costs. The paper sets out the actions being taken to mitigate these risks and the Committee is asked to note these.
3.1The Committee is asked to note the details provided and to note the actions being taken to mitigate the risks described.
4 DETAIL
4.1The Pathfinder North 1 (PFN1) contract provided connections to 145 sites in Argyll and Bute. Our cost was £367k p.a. which was a lot less than the real cost of this service due to the substantial subsidy from the Scottish Government. The full annual cost of these connections was £1.48m p.a.. The contract expired on 20 March 2014.
4.2As previously reported to Council, we agreed to delay implementation of SWAN services until early 2016 in order to enable Partners to benefit from the Next Generation Broadband (NGB) infrastructure rolled out by BT across the Highlands & Islands area.
4.3Final pricing for a contract extension was confirmed by Cable & Wireless on 19 December 2012 with the price for Argyll and Bute Council sites finalised at £814,330 p.a. This was for a 2 year contract extension from 21 March 2014 to 20 March 2016 and also allows for up to 6 months extension as part of a handover period to a new service provider. Scottish Wide Area Network (SWAN) update 4.4 Following approval by Council of the PFN2 business case on 13 February 2014, a new Minute of Agreement was eventually signed by us in July 2015 between the new PFN2 partners (now including Western Isles and excluding Shetland) to bind partners together and allowing Highland Council to sign both a SWAN Membership Agreement with NHS National Services Scotland (NSS) on behalf of Pathfinder North 2 partners and a Call-Off contract with Capita.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BROADBAND PATHFINDER NORTH UPDATEReport | 82 KB | DownloadRead as text |
Follow Policy and Resources Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Aug 2026 | Financial monitoring overview – 30 june 2026Decision The Policy and Resources Committee – 1. agreed to recommend that Council approve the budget changes in Secti... | Agreed | Open |
| 20 Aug 2026 | Budget outlook 2027-28 to 2031-32Decision The Policy and Resources Committee noted the current Budget Outlook position for the period 2027-28 to 2031-... | Noted | Open |
| 20 Aug 2026 | Potential impact of iran conflict - updateDecision The Policy and Resources Committee noted the content of the submitted report. (Reference: Report by Section ... | Noted | Open |
| 20 Aug 2026 | Funding request from local organisationsDecision The Policy and Resources Committee – 1. agreed to award a one-off grant of £36,000, to be paid from the Prio... | Agreed | Open |
| 20 Aug 2026 | Scottish languages act 2025 - areas of linguistic significanceDecision The Policy and Resources Committee – 1. noted the progress being made to ensure that the Council meets its s... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.