Resolved
Decision The Committee noted the content of the report. (Ref: Report by Senior Development Officer dated 11 th April 2016, submitted).
Oban Lorn & The Isles Area Committee noted this item on Monday 11 April 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Committee noted the content of the report. (Ref: Report by Senior Development Officer dated 11 th April 2016, submitted).
1.1This report provides an update on the various digital infrastructure projects including: Next Generation Broadband o BT commercial programme o Highlands and Islands Programme o Community Broadband Scotland o Extension of Funding Mobile Communications o Mobile Infrastructure Project o Scottish Government Pilot on Coll o Vodafone Rural o Commercial upgrades Public Wi-Fi
It is recommended that Oban, Lorn and the Isles Area Committee 1. Note the content of this report. ARGYLL AND BUTE COUNCIL OBAN, LORN AND THE ISLES AREA COMMITTEE
Development and Infrastructure 13 APRIL 2016
Digital Infrastructure Update
2.0INTRODUCTION
2.1Work has commenced on a number of programmes which aim to improve the digital infrastructure across Argyll. This report provides an update on the various projects within the Oban, Lorn And The Isles area.
3.1It is recommended that Oban, Lorn And The Isles Area Committee 1. Note the content of this report.
4.0DETAIL
The work being undertaken in relation to digital infrastructure relates to broadband or mobile communications.
4.1Next Generation Broadband
Next generation broadband within Oban, Lorn And The Isles is being delivered through one of three programmes – the commercial programme by BT (parts of Oban), the Highlands and Islands project and Community Broadband Scotland supported community projects.
4.2Work continues on building the new infrastructure network to support next generation broadband. Having completed the subsea cable links in 2014, land based backhaul and local access fibre cables are required to connect communities. Whilst telephone exchanges will continue to provide a service in relation to telephone calls only a handful of exchanges will handle next generation broadband services, new access cables running from these “headend” exchanges directly to new communication cabinets within communities will ensure that the superfast speeds reach the local cabinets.
4.3During 2015 and early 2016, we have seen new connections which mean that more residents in the OLI area can now access fibre services including the first connections on Mull within the Craignure and Tobermory exchange areas. Work continues in many locations to extend the fibre services to as many premises as possible within the budget of the project and further connections are expected during 2016. A summary of all exchanges across OLI is contained at Appendix 1. 4.4 Once the new fibre cabinets are live, customers who want access to superfast broadband must order the upgraded fibre service from their internet service provider. Members of the public can check whether they are able to order a next generation service at www.scotlandsuperfast.com/where-when. If they are not able to order a next generation broadband service they will be given an indication of whether the service is likely to be available within their exchange area and if so when the first premises are expected to be connected.
4.5BT commercial programme The commercial rollout by BT has connected some premises in Oban through 2015.
4.6Highlands and Islands Programme The Highlands and Islands (H&I) programme in Argyll is currently expected to connect 83% of premises when taken with the commercial rollout.
4.7The first live premises through the H&I programme were in Oban in September 2014 and during 2015 additional connections have been made within the Dalmally and Taynuilt exchange areas and latterly in Ledaig (for Benderloch area) and Craignure. During 2016, Tobermory and Balvicar exchange areas have also had their first fibre cabinets connected.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
DIGITAL INFRASTRUCTUREReport | 2 MB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.