Decision The Area Committee:- 1. Considered and noted the contents of the report and; 2. Thanked everyone involved in the implementation of the project. (Ref: Report by Special Projects and Quality Improvement Officer dated 13 th June 2018, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Oban. The new Oban High School Project is a Design Build Finance and Maintain (DBFM) Project being delivered as part of the Scottish Government’s Schools for the Future Programme.
1.2The Project reached Practical Completion on 5 April 2018.
1.3The decant of pupils, staff and resources took place as planned during the Easter holiday, and the school opened its doors to welcome pupils on Wednesday 18 April 2018.
1.4The Project has now entered Phase 2, which will continue through to February 2019. This Phase will include the demolition of the old Oban High School buildings, the construction of enlarged car parking and bus drop-off, and external social areas.
Recommendations
It is recommended that Members consider the content of this report.
1 ARGYLL AND BUTE COUNCIL OLI AREA COMMITTEE
CUSTOMER SERVICES 13 JUNE 2018
NEW SCHOOLS REDEVELOPMENT PROJECT OBAN HIGH SCHOOL UPDATE
2.0INTRODUCTION
2.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Oban.
It is recommended that Members consider the content of this report.
4.0DETAIL
4.1The new Oban High School Redevelopment Project is a Design Build Finance and Maintain (DBFM) Project being delivered as a part of the Scottish Government’s Schools for the future Programme pipeline with hubNorth Scotland Ltd, the Council’s project partner.
4.2Key Programme Dates The key contract programme dates for Oban High School are:
Date Description Comment 5 April 2018 Practical Completion reached New Oban High School 18 April 2018 opened as planned to pupils Demolition of existing school April 2018 – Phase 2 buildings, February External Works construction of 2019 car park, bus drop- off and landscaping All works completed February Phase 2 Completion and whole school 2019 availability
At this stage in the Phase 2 construction period, there is no change to the intended programme.
4.3Construction Update Following the completion of Phase 1, the main construction activities being progressed are: 2 The old Oban High School buildings have been handed over to Morrison Construction to allow preparation for demolition to commence; Ecological surveys have been undertaken prior to the start of the demolition; and Snagging works to the new building are taking place and are being reviewed on an ongoing basis. The playing surface of the existing 3G pitch at the school is due to be replaced. As part of the First Year of operation of the DBFM contract, the pitch will be resurfaced and new goal recesses added as part of the works. This work will take place and be completed during the forthcoming school summer holidays.
Images of the new Oban High School are included as Appendix 1.
4.4Health, Safety and Environmental Matters Throughout the whole of the Phase 1 Construction Period, the inspection of the site regarding performance on Environmental Matters found the works to be compliant, with no issues raised and with no RIDDOR (Reporting of Injuries, Diseases and Dangerous Occurrences Regulations) accidents or injuries.
4.5Decant The Exceptional Closure Days granted by the Scottish Government to facilitate the decant took place as planned on Wednesday 28 March, Thursday 29 March, Monday 16 April and Tuesday 17 April 2018.
All of the teaching materials and resources were transferred to the new school during the Easter holidays, including all of the identified Legacy Items, which now have pride of place in the new school foyer.
The school provided an Easter revision programme for senior pupils during the holidays, arranged with and hosted by Argyll College.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.