Resolved
Decision The Bute and Cowal Area Committee considered and noted the contents of the report. (Ref: Report by Special Projects & Quality Improvement Manager dated 4 June 2019, submitted)
Bute and Cowal Area Committee noted this item on Tuesday 4 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Bute and Cowal Area Committee considered and noted the contents of the report. (Ref: Report by Special Projects & Quality Improvement Manager dated 4 June 2019, submitted)
It is recommended that Members note and consider the content of this report.
4.0DETAIL
4.1The Council’s Dunoon Primary School redevelopment project is a Design Build Direct Agreement (DBDA) that is being delivered as part of the Scottish Government’s Schools for the Future Programme pipeline, through hubNorth Scotland Ltd (hubNorth), the Council’s project partner.
Contract Close was reached on Monday 3 July 2017.
4.2Programme Dates The key construction dates and phases for the Dunoon Primary School Redevelopment Project are:
2 Date Description Comment June 2017 Decant of all resources Completed from West to East Wing; Dunoon ELC to Kirn ELC; ESCAPE to Girl Guiding Hall, Dunoon.
3 July 2017 Contract Close
10 July 2017 Tier 1 Contractor moved Phase 1 is divided into on site to commence two sub-phases 1A Phase 1 of the Works. and 1B
July 2017 Phase 1A: Completed
July – Phase 1B: Completed November September 2017 2017 July 2017 – Phase 2 Refurbishment of Completed November November West Wing and new 2018 2018 Energy Centre constructed. Now underway November Pupils/Staff decant from Dunoon ELC remain at 2018 Decant East Wing to refurbished Kirn ELC; West Wing ESCAPE remains at Guide Hall. December Phase 3 East Wing Demolition 2018 – and construction of November new East Wing works 2019 ongoing November Whole school occupation Whole school 2019 available for occupation – demolition of exisiting separate games hall building to commence November Phase 4 Final demolition 2019 – (existing Games Hall) January 2010 and site clearance
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
NEW SCHOOLS REDEVELOPMENT PROJECT UPDATE FOR DUNOON PRIMARY SCHOOLReport | 472 KB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.