NEW SCHOOLS REDEVELOPMENT PROJECT, OBAN HIGH SCHOOL UPDATE
NotedCommittee1 paper
Oban Lorn & The Isles Area Committee noted this item on Wednesday 13 March 2019. Below is the council's own wording, with the papers it was decided on.
Decision The Oban, Lorn and the Isles Area Committee: 1. Considered and noted the contents of the report and; 2. Thanked the Special Projects Manager and his team for their hard work and continued communication with the Committee. (Ref: Report by Special Projects Manager dated 29 January 2019, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Oban. The new Oban High School Project is a Design Build Finance and Maintain (DBFM) Project being delivered as part of the Scottish Government’s Schools for the Future Programme.
1.2Oban High School achieved formal handover following sign off by the Independent Tester on 5 April 2018. The decant of pupils, staff and resources took place as planned during the Easter holiday, and the school opened its doors to welcome pupils on Wednesday 18 April 2018. Phase 2, which will continue through to March 2019, includes the demolition of the old Oban High School buildings, the construction of enlarged car parking and bus drop-off, and external social areas, and is progressing well, notwithstanding the programme delay. The contractor has experienced delay due to additional work to remove foundations.
1.3The tenth quarterly newsletter was issued in December, and was also made available through the dedicated Oban High School project website, hosted by Morrison Construction, at www.ohsproject.co.uk
1.4The Council’s Special Projects Team, along with the FM company FES FM, continue to hold regular meetings with the Head Teacher to discuss any issues within the school, along with ensuring all Health and Safety matters are addressed as contractually required.
Recommendations
It is recommended that Members consider the content of this report.
1 ARGYLL AND BUTE COUNCIL OLI AREA COMMITTEE
CUSTOMER SERVICES 13 MARCH 2019
NEW SCHOOLS REDEVELOPMENT PROJECT OBAN HIGH SCHOOL UPDATE
2.0INTRODUCTION
2.1This report provides Members with progress on the Council’s Schools Redevelopment Project in partnership with hubNorth Scotland Ltd (hubNorth) to build a new secondary school in Oban.
It is recommended that Members consider the content of this report.
4.0DETAIL
4.1The new Oban High School Redevelopment Project is a Design Build Finance and Maintain (DBFM) Project being delivered as a part of the Scottish Government’s Schools for the future Programme pipeline with hubNorth Scotland Ltd, the Council’s project partner.
4.2Key Programme Dates The key contract programme dates for Oban High School are:
Date Description Comment 5 April 2018 Practical Completion reached New Oban High School 18 April 2018 opened as planned to pupils Demolition of existing school April 2018 – Phase 2 buildings, March 2019 External Works construction of car park, bus drop- off and landscaping All works completed March 2019 Phase 2 Completion and whole school availability
4.3Construction Update Following the commencement of Phase 2, the main activities that have been progressed are: Demolition works have been completed Groundworks to the car parking and bus drop off areas have 2 commenced Stone dykes and kerbing works are progressing well Attenuation tanks installed Cycle shelters have been installed
Images of Works are included as Appendix 1.
4.4Future Works Completion of soft landscaping Completion of hard landscaping, car parking and external seating areas Completion of stone dykes and kerbing works Installation of external lighting and cctv
4.5Communications The tenth quarterly newsletter was made available through the dedicated project website at www.ohsproject.co.uk. The website, hosted by Morrison Construction, has a direct link available from the home page on the Oban High School website.
4.6Health, Safety and Environmental Matters Throughout the whole of the Phase 1 Construction Period, the inspection of the site regarding performance on Environmental Matters found the works to be compliant, with no issues raised and with no RIDDOR (Reporting of Injuries, Diseases and Dangerous Occurrences Regulations) accidents or injuries.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv...
Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.