Resolved
Decision The Bute and Cowal Area Committee considered and noted the progress update provided in the report. (Ref: Report by Rothesay Pavilion Project Manager dated 23 January 2019, submitted)
Bute and Cowal Area Committee noted this item on Tuesday 5 March 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Bute and Cowal Area Committee considered and noted the progress update provided in the report. (Ref: Report by Rothesay Pavilion Project Manager dated 23 January 2019, submitted)
1.1The purpose of this report is to provide members with a progress update on the Rothesay Pavilion Adaptive Restoration and Extension Works project, being delivered by CBC Ltd (CBC).
Bute and Cowal Area Committee is asked to consider and note:
2.1The progress update provided in this report.
2.2The financial performance of the project, as set out in Appendix 1 to this Report.
1 ARGYLL AND BUTE COUNCIL Bute and Cowal Area Committee
DEVELOPMENT & INFRASTRUCTURE 5th March 2019 SERVICES
Rothesay Pavilion Progress Report
3.0INTRODUCTION
3.1The project comprises the comprehensive refurbishment of the grade A listed Rothesay Pavilion which is a key component of the Council’s ambitious and forward looking programme to assist regeneration and economic development in five of its waterfront towns; Campbeltown, Helensburgh, Oban, Rothesay and Dunoon.
3.2The project will bring Rothesay Pavilion back into viable economic use by allowing a mix of new commercial, cultural and community activities to be provided within it. This will bring new life to this iconic building as well as stimulating wider regeneration and local economic activity.
3.3On completion the building will be managed by Rothesay Pavilion Charity (RPC) who will lease the building from the Council for a term of 25 years. The charity’s board comprises a mix of people who live on the island or who have links to it.
3.4Full funding for the project was achieved in September 2017 and a construction contract was awarded to Messrs CBC on 29th November 2017 with a projected completion date of 31st July 2019.
Bute and Cowal Area Committee is asked to consider and note:
4.1The progress update provided in this report.
4.2The financial performance of the project as set out in Appendix 1 to this Report.
2 5.0 DETAIL
Programme Delivery
5.1As previously reported the main contractor CBC have been on site since 29th November 2017 and at the end of January 2019 the percentage of programme passed on the original contract duration of 87 weeks is 70% (61 weeks).
5.2The overall percentage of work completed equates to 50% at week 61.
Key Work Package completion rates, are as follows:
Work Package Previous Current Variance Trend Report Report (%) (▲/► ) Quarter (%) Quarter (%) Early Enabling 100 100 0 Complete Works CDP Design 76 87 11 ▲ Approval - Manufacture Roof Works 39 59 20 ▲ New Office 67 86 19 ▲ Extension (1st Floor) Upper Ground 67 67 0 ► Floor Alterations Main Hall/Exhibit 74 76 2 ▲ Space/Stage/ Changing Rooms Toilet/Shop 77 86 9 ▲ Extension Utilities 5 5 0 ► External Envelope 26 56 30 ▲ Works Internal Fit Out 2 11 9 ▲ Caretakers House 22 46 24 ▲
5.3As reported above, 70% of the contract duration has expired, 41% of the contract sum has been expended which is 16% below the Main Contractors cash flow forecast for this stage of the project’s delivery. It should be noted this is an 8% improvement compared to the previous report. With 50% of the work completed to date and actual spend not having met the contractors cash flow forecast, it is reasonable to draw the conclusion the Main Contractor remains behind programme as a consequence of works having not progressed either at the same speed or in the same sequence as was originally planned. The main areas of delay in terms of spend, are as follows:
Under croft / substructure works progressed at a much slower rate than anticipated and unexpected site conditions also led to changes in the lift pit design/works in the immediate vicinity; An initial delay in the provision of temporary protection to the roof and
3 abandonment of an over roof has had an impact to follow on works: concrete repairs, replacement roof finish, roof lights, parapet works and cast stone copings;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ROTHESAY PAVILION PROGRESS REPORTReport | 1.9 MB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.