Decision The Bute and Cowal Area Committee: Noted the contents of the report and; Agreed that Port Bannatyne should be added to the list of Bute and Cowal communities to be considered for festive funding, on the basis that the Council has historically provided ad-hoc support to the project. (Ref: Report by Transformation Project Manager dated 11 February 2019, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1The purpose of this report is to update members on the delivery of festive lighting across Bute and Cowal in 2018, as well as the community handover arrangements now that the Council is ceasing to provide this non-statutory service.
1.2Overall the outlook is very positive, and it is expected that community arrangement in place, at least in principle, by the end of this financial year. Each situation is slightly different from the last in terms of the historic provision; as well as the mix of skills, funding and capacity available to communities, with the result that this is a complex piece of work.
Recommendations
Members are asked to:
Note the contents of this report;
Agree that Port Bannatyne should be added to the list of Bute and Cowal communities to be considered for festive funding, on the basis that the Council has historically provided ad-hoc support to the project. ARGYLL AND BUTE COUNCIL BUTE AND COWAL AREA COMMITTEE
DEVELOPMENT AND 5 MARCH 2019 INFRASTRUCTURE
FESTIVE LIGHING UPDATE
2.0INTRODUCTION
2.1This report provides Members with an update on the delivery of festive lighting across Bute and Cowal in 2018. The overall programme saw a mix of council- led and community-led festive lighting displays.
2.2As per the Budget decision of February 2016, the Council is no longer in a financial position to deliver festive lighting. Community handovers are at various stages, with some complete and some still in progress.
Members are asked to:
3.1Note the contents of this report; and
3.2Agree that Port Bannatyne should be added to the list of Bute and Cowal communities to be considered for festive funding, on the basis that the Council has historically provided ad-hoc support to the project.
4.0DETAIL
4.1DELIVERY OF FESTIVE LIGHTING 2018
4.1.1 Festive lighting in Bute and Cowal was delivered as follows:
Delivery mechanism Town/village Comments Council Community Dunoon Dunoon Presents The BID received (PA23 BID) funding of £8,000 from delivered this event ABC. via local contractor John Brown (Strone) Rothesay ABC delivery The switch on event itself in Rothesay was cancelled due to adverse weather.
No community delivery partner has been identified in Rothesay, however, a number of options are being considered.
Innellan Community Council Previously established community delivery method e.g. pre-2016 Sandbank Community Council Previously established community delivery method e.g. pre-2016 Port Christmas This is an addition to Bannatyne Committee lists reported previously to members.
There is a pre-2016 community event in this area, however, this has been added for the sake of completeness because the Council had historically provided some assistance to this event, with the result that local members might wish to consider allocating some of the remaining funds to this group.
4.2FINANCIAL POSITION
4.2.1 The estimated balance of the B&C festive fund is noted in the table below. The total costs are not fully reconciled in the ledger because timesheets require to be verified and final invoices are awaited from suppliers/sub-contractors. The exact balances will be available after the end of the financial year. 2017/18 2018/19 2018/19 spend (or Area Balance spend budget committed) BC 27,345 24,557 8,000 in grants c. 11,000
Repairs and labour TBC
4.2.2 The Environment, Development and Infrastructure Committee, at its meeting of 7 March 2018, will consider a paper on festive lighting which includes a suggested guide for area committees to use in order to establish their pro-rata allocation of the remaining funds.
5.0CONCLUSION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with...
Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.