Environment, Development and Infrastructure Committee noted this item on Thursday 7 March 2019. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. Noted the successful delivery of festive lighting schemes across Argyll and Bute in 2018. 2. Endorsed the work of community groups to deliver festive lighting in their towns and villages. 3. Agreed the scoring matrix guide for Area Committees as set out at paragraph 4.2.2 of the submitted report. 4. Noted that the Council has now ceased to provide this service and that the project is on track to deliver full community handovers by the end of this financial year. 5. Noted that other local authorities have approached the Council for advice and support in their own festive handover initiatives. (Reference: Report by Executive Director – Development and Infrastructure Services dated March 2019, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The purpose of this report is to update members on the delivery of festive lighting across Argyll and Bute in 2018, as well as the community handover arrangements now that the Council is ceasing to provide this non-statutory service.
1.2Overall the outlook is very positive, and it is expected that all areas will have a community arrangement in place by the end of this financial year. Each situation is slightly different from the last in terms of the historic provision; as well as the mix of skills, funding and capacity available to communities, with the result that this is a complex piece of work.
Recommendations
Members are asked to:
Note the successful delivery of festive lighting schemes across Argyll and Bute in 2018;
Endorse the work of community groups to deliver festive lighting in their towns and villages;
Agree the scoring matrix guide for area committees as set out at 4.2.2;
Note that the Council has now ceased to provide this service and that the project is on track to deliver full community handovers by the end of this financial year;
Note that other local authorities have approached the Council for advice and support in their own festive handover initiatives. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE
DEVELOPMENT AND 7 MARCH 2019 INFRASTRUCTURE SERVICES
FESTIVE LIGHTING UPDATE
2.0INTRODUCTION
2.1This report provides Members with an update on the delivery of festive lighting across Argyll and Bute in 2018. The overall programme saw a mix of council-led and community-led festive lighting displays.
2.2As per the Budget decision of February 2016, the Council is no longer in a financial position to deliver festive lighting. Community handovers are at various stages, with some complete and some still in progress.
Members are asked to:
3.1Note the successful delivery of festive lighting schemes across Argyll and Bute in 2018;
3.2Endorse the work of community groups to deliver festive lighting in their towns and villages;
3.3Agree the scoring matrix guide for area committees as set out at 4.2.2;
3.4Note that the Council has now ceased to provide this service and that the project is on track to deliver full community handovers by the end of this financial year;
3.5Note that other local authorities have approached the Council for advice and support in their own festive handover initiatives.
4.0DETAIL
4.1DELIVERY OF FESTIVE LIGHTING 2018
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.