CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council

FESTIVE LIGHTING COMMUNITY TRANSITION - END PROJECT REPORT

Noted Committee 1 paper

Environment, Development and Infrastructure Committee noted this item on Thursday 5 March 2020. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

Decision The Environment, Development and Infrastructure Committee – 1. Endorsed the positive work of communities across Argyll and Bute to deliver their own festive lighting schemes. 2. Noted the significant amount of support provided by the Council’s street lighting team to communities to ensure effective transitions. 3. Noted the detail in the submitted report on festive community engagement. 4. Agreed that this general approach would be taken to the winter maintenance community engagement project, with further detail to be reported to the next Environment, Development and Infrastructure Committee following the initial scoping work outlined at paragraph 3.15 of the submitted report. (Reference: Report by Interim Executive Director with responsibility for Roads and Infrastructure Services dated February 2020, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

Recommendations

2.1Members are asked to:

i. Endorse the positive work of communities across Argyll and Bute to deliver their own festive lighting schemes;

ii. Note the significant amount of support provided by the Council’s street lighting team to communities to ensure effective transitions;

iii. Note the detail in this report on festive community engagement; and agree that this general approach will be taken to the winter maintenance community engagement project, with further detail to be reported to the next EDI committee following the initial scoping work outlined at 3.15 of this report.

Background

3.1The Council, at its budget meeting in February 2016 agreed to a savings package where the revenue budget of £100,000 per annum for festive lighting was removed. An earmarked sum of £300,000 from the Council’s reserves was made available to support Council delivery and community-transition for three further years (up to December 2018).

3.2The below table provides a chronology of reporting on this subject and the development of the project since the Budget meeting of 2016:

Committee Comments EDI August 2016 This report baselined the varied historic arrangements in the 21 towns and villages where the Council delivered festive lighting.

The specification and existing levels of community involvement differed from town to town and village to village.

In December 2016 the Council commissioned an external contractor to deliver festive lighting to the historic specification while a community engagement plan was developed. EDI April 2017 This report provided an update on Council-led delivery for Christmas 2016, and confirmed that community engagement was underway.

The Committee agreed to evenly split the remaining festive funds c.£200,000 on an area by area basis (c.£50,000 per area) EDI Sept 2017 This update outlined the initial steps of community engagement and the generally positive feedback.

Members noted that the Council would deliver in 2017 unless a group was ready to take on festive lighting in their town/village.

The committee also agreed that should groups wish to apply for funding any application would be subject to the normal process, with area committees to determine the applications in their areas.

For Christmas 2017 Helensburgh delivered their own event with the aid of £20,000 from the earmarked funds; Tobermory, Innellan and Sandbank delivered their own events independently.

The Council delivered festive lighting in all other locations via its internal street lighting team while discussions continued with community groups. At this point all areas where there was an existing group with some involvement in festive lighting agreed in principle to take festive lighting on.

There remained a few areas where there was no identified group to take the task on. EDI March 2018 This report updated members on the delivery of festive lighting for Christmas 2018.

The committee agreed to outline heads of terms to form the basis of community agreements as well as a strategy to transfer lighting assets to communities.

These documents supported the ongoing community engagement process, providing clarity on the respective roles and responsibilities of both parties.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
FESTIVE LIGHTING COMMUNITY TRANSITION: END PROJECT REPORTReport 107 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

11 of 18 attended
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourMember, present
GB
Councillor Gordon BlairMember, present
RC
Councillor Robin CurrieChair, present
DK
Councillor Donald KellyMember, apologies
DK
Councillor David KinniburghMember, present
DM
Councillor Donald MacMillan BEMMember, present
RM
Councillor Roderick McCuishMember, apologies
SJ
Councillor Sir Jamie McGrigorMember, apologies
JM
Councillor Jean MoffatMember, present
AM
Councillor Aileen MortonMember, present

All 18 on the meeting page

On this subject at Argyll and Bute

Search all
  1. FESTIVE LIGHTING COMMUNITY TRANSITION - END PROJECT REPORTThis decision
  2. Festive lighting updateNoted
  3. Festive lighting updateNoted
  4. Festive lightingNoted
  5. Festive LightingAgreed
  6. Festive lighting updateNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies