Resolved
Decision The Bute and Cowal Area Committee considered and noted the progress update provided in the report. (Ref: Report by Rothesay Pavilion Project Manager dated 25 April 2019, submitted)
Bute and Cowal Area Committee noted this item on Tuesday 4 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Bute and Cowal Area Committee considered and noted the progress update provided in the report. (Ref: Report by Rothesay Pavilion Project Manager dated 25 April 2019, submitted)
1.1The purpose of this report is to provide members with a progress update on the Rothesay Pavilion Adaptive Restoration and Extension Works project, being delivered by CBC Ltd (CBC).
1.2The construction contract started on site on 29th November 2017 with a completion date of 31st July 2019.
1.3The practical completion date has been extended to 3rd September 2019. This is 5 weeks beyond the original programme duration of 87 weeks. This is a consequence of work and weather related issues.
1.4The construction contract remains on budget at £10,688,023.
Bute and Cowal Area Committee is asked to consider and note:
2.1The progress update provided in this report.
1 ARGYLL AND BUTE COUNCIL Bute and Cowal Area Committee
DEVELOPMENT & 4th June 2019 INFRASTRUCTURE SERVICES
Rothesay Pavilion Progress Report
3.0INTRODUCTION
3.1The project comprises the comprehensive refurbishment of the grade A listed Rothesay Pavilion which is a key component of the Council’s ambitious and forward looking programme to assist regeneration and economic development in five of its waterfront towns; Campbeltown, Helensburgh, Oban, Rothesay and Dunoon.
3.2On completion the building will be managed by Rothesay Pavilion Charity (RPC) who will lease the building from the Council for a term of 25 years.
3.3Full funding for the project was achieved in September 2017 and a construction contract was awarded to Messrs CBC on 29th November 2017 with a contract completion date of 31st July 2019. Contract completion has subsequently been extended to 3rd September 2019.
3.4The project continues to prove both complex and challenging due to the location, design, age and unique characteristics of the Pavilion building.
Bute and Cowal Area Committee is asked to consider and note:
4.1The progress update provided in this report.
5.0DETAIL
Programme Delivery
5.1At the end of the 4th quarter (January - March 2019) the percentage of programme passed compared to the original contract duration of 87 weeks is 79% (69 weeks).
5.2The overall percentage of work completed at week 69 is 52%.
21 5.3 The Main Contractor has lodged 3 Claims for Extensions of Time (EOT) including loss and expense, namely:
Claim 1: (October 2018) for an EOT (5 weeks) and associated loss and expense in relation to under stage steelwork design alterations. Rejected.
Claim 2: was received on 23rd November notifying of delay (9 weeks), loss and expense associated with the Café, Kitchens and Bars tender that exceeded the provisional sum by 92% (£126k) necessitating a value engineering exercise over a period of 6-7 weeks. Award of 5 weeks approved resulting in a revised practical completion date of 3rd September 2019.
Claim 3: delays associated with Asbestos removal works to the main hall ceiling. Research and development work is in progress by the Design Team and Council appointed Specialist Asbestos Consultants (ACS Physical Risk Ltd) regarding options, cost and time implications to minimise the risk to the Council.
5.4Key Contract Work Package completion rates, are as follows:
Work Package Previous Current Variance Trend Report Report (%) (▲/► ) Quarter (%) Quarter (%) Early Enabling Works 100 100 0 Complete CDP Design Approval - 87 92 5 ▲ Manufacture Roof Works – Main Roof 59 64 5 ▲ New Office Extension (1st 86 86 0 ► Floor) Upper Ground Floor 67 68 1 ▲ Alterations Main Hall/Exhibit 76 81 5 ▲ Space/Stage/ Changing Rooms Toilet/Shop Extension 86 93 7 ▲ Utilities 5 5 0 ► External Envelope Works 56 66 10 ▲ Internal Fit Out 11 16 5 ▲ Caretakers House 46 47 1 ▲
5.5As reported above, 79% of the contract duration has expired and with only 52% of the work completed to date the Main Contractor remains behind programme. This has been primarily caused due to works e.g. undercroft excavation, roof replacement, cast stone repairs & cast stone coping replacement, not having progressed at the same speed, due to weather and complexity challenges.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
ROTHESAY PAVILION PROGRESS REPORTReport | 14 MB | DownloadRead as text |
Follow Bute and Cowal Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2026 | Charts (argyll and the isles)Decision The Bute and Cowal Area Committee considered and noted the information provided in the presentation. (Refere... | Noted | Open |
| 1 Sep 2026 | Area committee quarterly performance reports fq1 2026/27Decision The Bute and Cowal Area Committee noted the performance and supporting commentary as presented. (Reference: ... | Noted | Open |
| 1 Sep 2026 | Supporting Communities Fund 2026/27Decision The Bute and Cowal Area Committee agreed that the 20 applications, marked as ‘Award’ or ‘Partial Award’ with... | Agreed | Open |
| 1 Sep 2026 | Roads and infrastructure services updateDecision The Bute and Cowal Area Committee noted the contents of the report. (Reference: Report by Executive Director... | Noted | Open |
| 1 Sep 2026 | Cruach mhor and clachan flats windfarm trustsDecision The Bute and Cowal Area Committee noted these updates, which are the most recent of the annual updates requi... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.