Resolved
Decision The Oban, Lorn and the Isles Area Committee noted and considered the content of the report. (Reference: Report by Executive Director with responsibility for Commercial Services dated 24 January 2020, submitted)
Oban Lorn & The Isles Area Committee noted this item on Wednesday 11 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Oban, Lorn and the Isles Area Committee noted and considered the content of the report. (Reference: Report by Executive Director with responsibility for Commercial Services dated 24 January 2020, submitted)
1.1The purpose of this report is to provide members of the Area Committee with an update on Estates and Property Development projects ongoing in the Oban, Lorn and the Isles Area.
2.1That the members:-
2.1.1 Note and consider the content of this update report on property related projects in the Oban, Lorn and the Isles area. ARGYLL AND BUTE COUNCIL OBAN, LORN AND THE ISLES – AREA COMMITTEE
COMMERCIAL SERVICES 11th MARCH 2020
PROPERTY UPDATE
3.0INTRODUCTION
3.1The purpose of this report is to provide members of the Area Committee with an update on Estates and Property Development projects ongoing in the Oban, Lorn and the Isles Area.
4.0CAR PARK PROJECT – HOTEL & CAR PARK OPPORTUNITIES
4.1The Estates and Property Development Team (E&PD) marketed three operational car parks (Albany Street, Tweeddale Street and the Esplanade) in Oban during 2018. The aim was to assess the market demand for development opportunities and to see if this could be met by maximising the use of existing assets. The key aims of the process were to maximise the economic return to the Council and the wider Oban area while seeking to maintain or enhance the parking provision in the town.
4.2An update report was provided to the OLI Business Day on 13th February 2019 at which time the following position was reported:
The DMT on 22nd January 2019 approved a report to select 4 preferred developers to take forward development on the 3 car parks. Officers will be working with the preferred developers over the coming months to move towards concluding contractual agreements and then planning submissions as required for the following proposed developments.
4.3Subsequent to this report officers from Estates and Property Development have met with the preferred developers for each of the sites to progress their proposals.
4.4Any development of the Albany Street site is contingent on providing alternative parking and the Tweeddale Street car park is currently being assessed for this purpose. Phase 1 site investigations were procured through HUB North and were returned week commencing 12th August 2019.
4.5The results of the phase 1 site investigations have been assessed by the 2 preferred developers and the specification of the phase 2 site investigations has been agreed to ensure it meets their requirements. HUB North were instructed on 15th October 2019 to procure the phase 2 site investigations which will require trial pits and boreholes to be completed in the car park. These works will be co-ordinated with the Roads Section to ensure that any disruption is minimised and are anticipated to be undertaken in February 2020.
5.0OBAN AIRPORT BUSINESS PARK
5.1Oban Airport Business Park was marketed in late 2018 however limited interest was received. Following further feedback it was apparent that there were a number of parties who were interested in the location but they had concerns about the costs of development. This was particularly in relation to the provision of services and the ground conditions at this location.
5.2To progress matters the Estates and Property Development team procured Ryder Architecture to look at the main constraints in connection with developing the site and to provide proposed layouts together with an assessment of the anticipated costs of providing serviced sites.
5.3This information was to allow a decision to be made on whether it is cost effective to proceed with further investment at the site and whether this should be done on a phased basis and only where serious occupier demand can be confirmed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
PROPERTY UPDATEReport | 83 KB | DownloadRead as text |
Follow Oban Lorn & The Isles Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Public question time part 1It was agreed therefore that the responses would not be read out but included in the minute and also emailed to the A... | Agreed | Open |
| 9 Sep 2026 | CHARTS (Argyll and Isles)Decision The Oban, Lorn and the Isles Area Committee considered and noted the information provided in the presentatio... | Noted | Open |
| 9 Sep 2026 | Roads and infrastructure updateDecision The Oban, Lorn and the Isles Area Committee noted the contents of the report. (Reference: Report by Executiv... | Noted | Open |
| 9 Sep 2026 | Oban PVA Flood Risk Management UpdateDecision The Oban, Lorn and the Isles Area Committee:- 1) considered the contents of this report; and 2) noted the co... | Noted | Open |
| 9 Sep 2026 | Argyll Square Project: Consolidated Financial Report and Delivery UpdateDecision The motion was carried by 4 votes to 2 and the Committee resolved accordingly. (Reference: A report by Secti... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.