Resolved
Decision The Argyll and Bute Harbour Board agreed to endorse the report. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated August 2020, submitted)
Argyll and Bute Harbour Board agreed this item on Thursday 10 September 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Argyll and Bute Harbour Board agreed to endorse the report. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated August 2020, submitted)
1.1This report provides Members with an update on ongoing major, and/or noteworthy, schemes currently being addressed within the Council’s Marine Asset Management Plan. Close liaison with Transport Scotland, CMAL and Calmac ensures that priorities are targeted accordingly.
1.2Capital works programmed for this financial year, 2020 to 2021, totals £4.2 million. The Asset Management Plan lists the work to be carried out over 10 years (the current year and following 9 years) across the entire marine infrastructure; it also provides indicative budgets. Currently, the overall costs for planned works is approximately £90million. A report will come forward later in the year to provide Members with the latest version of the updated asset management plan, along with estimates, details of the funding model and potential effects on fees and charges.
1.3In particular, this report provides an update on the following schemes:-
• Craignure • Iona and Fionnphort • Rothesay Harbour • Rothesay Pontoons • Link-spans – general
1.5Members are asked to endorse this report. ARGYLL AND BUTE COUNCIL HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES 10 SEPTEMBER 2020
MARINE ASSET MANAGEMENT PLAN
2.0INTRODUCTION
2.1This report provides Members with a further update on ongoing major, and/or noteworthy, schemes currently being addressed within the Council’s Marine Asset Management Plan.
3.1Members are asked to endorse this report.
4.0Close liaison with Transport Scotland, CMAL and Calmac ensures that priorities can be established in the Asset Management Plan and targeted accordingly.
4.1In particular, this report provides an update on the following schemes:-
• Craignure • Iona and Fionnphort • Rothesay Harbour • Rothesay Pontoons • Link-spans - general
5.0DETAIL - The Asset Management Plan:-
5.1Detail is provided below, and in the attached appendices, for some of the more major, or notable, schemes in the Asset Management Plan to provide Members with an indication of progress. Capital works programmed for this financial year, 2020 to 2021, totals £4.2 million.
5.2The Asset Management Plan lists the work to be carried out over 10 years (the current year and following 9 years) across the entire marine infrastructure; it also provides indicative budgets. Currently, the overall costs for planned works is approximately £90million. A report will come forward later in the year to provide Members with the latest version of the updated asset management plan, along with estimates, details of the funding model and potential effects on fees and charges.
5.3Craignure Pier:-
The ‘Interim Options’ Outline Business Case (OBC) for Craignure Pier is now at ‘final draft’ stage and findings will shortly be made available to stakeholders and the general public. The consultant Turner and Townsend was recently commissioned by the Council to progress the long-term OBC – anticipated to be complete before the spring of next year. Appendix A provides details of interim-option costs and key milestone dates for the next phase.
5.4Fionnphort / Iona Ferry Slips –
As previous reported, a brief for sedimentation modelling was awarded to the specialist consultant ‘JBA Consulting’, in late 2019 and their work is now complete. Findings from the sedimentation modelling suggest that deposition of sediment on the Iona coastline is greater than on the Fionnphort side; whilst these results will not impede current plans to progress both schemes, further analysis of results will be required along with possible reconsideration of current proposals for Iona.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
MARINE ASSET MANAGEMENT PLANReport | 1.1 MB | DownloadRead as text |
Follow Argyll and Bute Harbour Board at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Oct 2026 | Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... | Noted | Open |
| 9 Oct 2026 | Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... | Agreed | Open |
| 9 Oct 2026 | Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... | Noted | Open |
| 9 Oct 2026 | Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... | Noted | Open |
| 9 Oct 2026 | Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.