Decision The Argyll and Bute Harbour Board; 1. considered the update on ongoing major and noteworthy schemes currently being taken forward via the Council’s Marine Asset Management Plan; 2. noted that £10.335 million worth of capital words have been programmed for the forthcoming finical year, 2021 to 2022; and 3. agreed that subject to confirmation of the position of the Craignure Marine Infrastructure Liaison Group, that the Chair and Vice-Chair contact Transport Scotland on behalf of the Board requesting that smaller vessels, similar to the MV Mull, be deployed between Craignure and Oban to provide a higher frequency and lower impact service with shore facilities to an appropriate scale in accordance to the vessels capacity. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated February 2021, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides Members with a further update on ongoing major, and/or noteworthy, schemes currently being addressed within the Council’s Marine Asset Management Plan.
1.2Capital works programmed for the forthcoming financial year, 2021 to 2022, are valued at £10.335 million, plus any underspend from schemes from this current financial year i.e. Rothesay Harbour.
1.3In particular, this report provides an update on the following schemes:-
Craignure Public consultation Work on linkspan Iona and Fionnphort Rothesay Harbour Piling and grouting works Pontoons Dunoon and Kilcreggan
1.4Members are asked to:- - consider the update on ongoing major and noteworthy schemes currently being taken forward via the Council’s Marine Asset Management Plan. - note that £10.335 million worth of capital words have been programmed for the forthcoming finical year, 2021 to 2022 ARGYLL AND BUTE COUNCIL ARGYLL AND BUTE HARBOUR BOARD
ROADS AND INFRASTRUCTURE SERVICES 4 MARCH 2021
MARINE ASSET MANAGEMENT PLAN
2.0INTRODUCTION
2.1This report provides Members with a further update on ongoing major, and/or noteworthy, schemes currently being addressed within the Council’s Marine Asset Management Plan.
Recommendations
3.1Members are asked to :- - consider the update on ongoing major and noteworthy schemes currently being taken forward via the Council’s Marine Asset Management Plan. - note that £10.335 million worth of capital words have been programmed for the forthcoming finical year, 2021 to 2022
Background
4.1Close liaison with Transport Scotland, CMAL and Calmac ensures that priorities can be established in the Asset Management Plan and targeted accordingly.
4.2In particular, this report provides an update on the following schemes:-
Craignure Public consultation Work on linkspan Iona and Fionnphort Rothesay Harbour Piling and grouting works Pontoons Dunoon and Kilcreggan
5.0DETAIL - The Asset Management Plan:-
5.1Detail is provided below on some of the more major schemes listed in the Asset Management Plan to provide Members with an indication of progress. Capital works programmed for the forthcoming financial year, 2021 to 2022, are valued at £10.335 million, plus any underspend from schemes from this current financial year i.e. Rothesay Harbour.
5.2The Asset Management Plan lists the work to be carried out on the Council’s marine infrastructure over the next 10 years.
5.3Craignure Pier – Public Consultation:-
At the time of writing this report, the public consultation on the future of Craignure Pier was live on the Council’s web site. The consultation provides information on both the ‘Interim Options’ Outline Business Case (OBC) and ‘Long Term Options’ OBC. A verbal update will be provided to Members at the Harbour Board Meeting on the outcome of the consultation.
5.4Craignure Pier – Work on the link-span:-
The first of the two hydraulic cylinders has been replaced at Craignure and work to replace the second cylinder is being planned for March with the help of the consultant ‘WSP’ and contractor RL Engineering. It is likely that work will take 3 days to complete, during which time, the pier at Craignure will be closed to all ferry traffic. Council officers are liaising closely with Calmac and, at the time of writing this report, the detailed programme for the works was being compiled
5.5Fionnphort / Iona Ferry Slips –
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.