Decision The Argyll and Bute Harbour Board – 1. Noted the update on significant and major programmes currently being addressed within Argyll & Bute Council’s Marine Asset Management Plan. 2. Noted that £15.5 million worth of capital works were programmed for the financial year 2022/2023 plus any slippage brought forward from 2021/2022. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated January 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report provides Members with an update on significant and major programmes currently being addressed within Argyll & Bute Council’s Marine Asset Management Plan.
1.2Capital works for the financial year 2022 / 2023 are valued at £15.5 million, plus any underspend from schemes from this current financial year e.g. Rothesay Harbour.
1.3Specifically this report provides an update on the following ongoing projects:
Craignure Long Term plan for a new terminal and marshalling area. Rothesay Harbour o Pontoons in the inner harbour area o Piling and grouting works Iona & Fionnphort breakwaters and overnight berthing facility
1.4The report also provides a summary of additional significant schemes added since the last report in March 2021 or included in the longer term Asset Management Plan.
RECOMMENDATIONS: Members of the Argyll and Bute Harbour Board are asked to:
a) Consider the update on significant and major programmes currently being addressed within Argyll & Bute Council’s Marine Asset Management Plan. b) Note that £15.5 million worth of capital works are programmed for the financial year 2022/2023 plus any slippage brought forward from 2021/2022. ARGYLL AND BUTE COUNCIL ARGYLL AND BUTE HARBOUR BOARD
ROAD AND INFRASTRUCTURE SERVICES 3 MARCH 2022
MARINE ASSET MANAGEMENT PLAN
2.0INTRODUCTION
2.1This report provides Members with an update on significant and major programmes currently being addressed within Argyll & Bute Council’s Marine Asset Management Plan.
Recommendations
3.1Members of the Argyll and Bute Harbour Board are asked to:
a) Consider the update on significant and major programmes currently being addressed within Argyll & Bute Council’s Marine Asset Management Plan. b) Note that £15.5 million worth of capital works are programmed for the financial year 2022/2023 plus any slippage brought forward from 2021/2022.
4.0DETAIL 4.1 Argyll & Bute Council continue close liaison with Transport Scotland, CMAL and CFL (CalMac) to ensure lifeline services and priorities are established in the Asset Management Plan and resources are targeted accordingly. The work carried out to support ferry traffic is generally financed through fees and charges which are used to service loans charges for capital borrowing.
4.2Detail is provided below on some of the significant schemes listed in the Asset Management Plan to provide Members with an indication of progress, in particular: Craignure Long Term plan for a new terminal and marshalling area. Rothesay Harbour o Pontoons in the inner harbour area o Piling and grouting works Iona & Fionnphort breakwaters and overnight berthing facility
4.3The programme of works for the 2022 / 2023 financial year are valued at £15.5 million, plus any underspend from the current financial year which include: Craignure Long Term plan, due to extended consultation Rothesay Harbour o Pontoons, due to unexpected ground conditions o Piling and grouting, due to tender issues and risk uncertainties
4.4Argyll & Bute Council’s Asset Management Plan covers a 10 year period on a rolling year by year basis and includes new or recent projects still in a design stage or without committed funding which include: Dunoon & Kilcreggan infrastructure and terminal upgrades to improve resilience and redundancy for the CFL ferry service to / from Gourock. Port Askaig new marshalling area to facilitate increased capacity of CFL ferry services to the port. Craignure Passenger Access System (PAS) renewal which replaces the existing PAS due to life expiry of the current equipment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.