ROADS AND INFRASTRUCTURE PROJECTS - COUNCIL FUNDED
NotedCommittee1 paper
Environment, Development and Infrastructure Committee noted this item on Thursday 2 June 2022. Below is the council's own wording, with the papers it was decided on.
Decision The Committee:- 1. Endorsed the overall programme of council funded projects being taken forward by Roads and Instructure Services; 2. Noted that a programme of street lighting column replacements will be brought to the Environment, Development and Infrastructure Committee in September 2022 and 3. Agreed to the Chair of the Environment, Development and Infrastructure approaching the Scottish Government with a view to securing additional resources to support the scheme to repair the damaged Bute sea wall. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated 24 May 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1This report provides Members with an update on schemes being taken forward by the Roads and Infrastructure Service which are substantially funded by budget allocations from the Council, as opposed to the other projects report on the agenda which provides detail on projects being taken forward with the benefit of external funding.
Recommendations
It is recommended that Members of the Environment, Development and Infrastructure Committee:
i. Endorse the overall programme of council funded projects being taken forward by Roads and Infrastructure Services.
ii. Note that a programme of street lighting column replacements will be brought to the Environment, Development and Infrastructure Committee in September 2022. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROADS AND INFRASTRUCTURE 2 JUNE 2022 SERVICES
ROADS AND INFRASTRUCTURE PROJECTS – COUNCIL FUNDED
2.0INTRODUCTION
2.1The report set out below provides Members of the Environment, Development and Infrastructure Committee with information on the projects and schemes being taken forward by the Roads and Infrastructure Service, funded by the Council.
It is recommended that Members of the Environment, Development and Infrastructure Committee:
i. Endorse the overall programme of council funded projects being taken forward by Roads and Infrastructure Services.
ii. Note that a programme of street lighting column replacements will be brought to the Environment, Development and Infrastructure Committee in September 2022.
4.0DETAIL
4.1COUNCIL FUNDED PROJECT SUCCESSES 2021/22
Project Investment Comments name Roads £10million 2021/22 Improvements to the road network, reconstruction supporting the local economy, tourism etc. programme More than 140 separate schemes across Argyll and Bute Footway and £500,000 Improvements to footways across the area active travel routes Modernised £200,000 Providing chip and pin options as well as cash parking payment We now have 64 parking terminals which offer multi payment options. Glengorm £1million New cell at the landfill site on Mull and landfill cell conversion of existing building to transfer and waste station. transfer station Securing the future efficiency of general waste collections on Mull up to the landfill ban in 2025, and providing efficient method to take material off the island for onward processing.
4.2ONGOING PROJECTS
Project name Investment Comments Roads £8million 2022/23 programme Improvements to the road reconstruction network, supporting the local economy, tourism programme etc.
Specific detail on this year’s programme is a separate item on this committee agenda. Footway and £500,000 Programme being developed which will be active travel reported to the September ED&I Committee. routes Route £100,000+ Project to use technology to provide efficiencies optimisation in vehicle routing and customer information/feedback on bin collections, with a view to expanding later to other works programming like gully cleaning, asset inspections etc. A procurement process is currently underway for this project with tender returns being assessed at the time of writing this report. Public £100,000 Scheme to install charging infrastructure at conveniences high-use PCs to help offset the cost of providing PCs, which are non-statutory.
Tender returns expected 20 May – will provide verbal update at meeting. Bute sea wall Circa Sea wall was damaged in storms December £1million 2021.
The team had to act immediately to put a temporary solution in place to protect the public road, utilities and nearby houses.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.