ROADS CAPITAL RECONSTRUCTION PROGRAMME 2022/23 UPDATE
NotedCommittee2 papers
Environment, Development and Infrastructure Committee noted this item on Thursday 2 June 2022. Below is the council's own wording, with the papers it was decided on.
Decision The Committee:- 1. Endorsed the approach taken to deliver the programme within budget given the price increases; and 2. Noted that the 2022/23 footway programme would be reported to the September Environment, Development and Infrastructure Committee. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated 20 May 2022, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE ROADS AND INFRASTRUCTURE SERVICES 2 JUNE 2022
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2022/23 UPDATE
1.0EXECUTIVE SUMMARY 1.1 Each year the Council through its annual budget setting process allocates budget for various capital projects. During this year’s budget setting process, the Council allocated £8m for roads reconstruction works. A programme of work was endorsed by the Environment, Development and Infrastructure (EDI) Committee in March 2022, following which information on projects for each administrative area was sent to Members. The March Environment, Development and Infrastructure Committee report and appendix can be found at item 6 in the link appended below, for ease of reference.
Environment, Development and Infrastructure Committee - 3 March 2022
1.2Since the programme was set, there have been significant international occurrences which have affected the prices of both fuel and bitumen. At the time of writing this report (early May) there has been a price increase of approximately 20% for coated roadstone. Whilst each of the planned schemes will be delivered, there will be less surfacing delivered than originally planned as a direct consequence of the price increase.
1.3It is recommended that the Environment, Development and Infrastructure Committee:
i. Endorses the approach taken to deliver the programme within budget given the price increases; and
ii. Note that the 2022/23 footway programme will be reported to the September Environment, Development and Infrastructure Committee. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE ROADS AND INFRASTRUCTURE SERVICES 2 JUNE 2022
ROADS CAPITAL RECONSTRUCTION PROGRAMME 2022/23 UPDATE
2.0INTRODUCTION 2.1 This report provides details of the roads reconstruction programme for 2022/23. The programme was initially based on an allocation of £5.378m which was increased to £8.0m at the Council’s Budget Meeting on 24 February 2022.
3.0RECOMMENDATIONS 3.1 It is recommended that the Environment, Development and Infrastructure Committee: i. Endorses the approach taken to deliver the programme within budget given the price increases; and
ii. Note that the 2022/23 footway programme will be reported to the September Environment, Development and Infrastructure Committee.
4.0DETAIL 4.1 A programme of work was endorsed by the Environment, Development and Infrastructure Committee in March 2022 following which information on projects for each administrative area was sent to Members. Since the programme was set there have been significant international occurrences which have affected the prices of both fuel and bitumen. At the time of writing (early May) there has been a price increase of approximately 20% for coated roadstone. Consideration was given to pausing the roads reconstruction programme however this was discounted on the basis that bitumen prices are not expected to reduce any time soon and more importantly pausing the programme would lead to an acceleration in deterioration which would ultimately cost more to correct.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.