CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Helensburgh & Lomond Area Committee, Tuesday 14 March 2023 at 9.30am

Helensburgh, Cardross and Dumbarton Cyclepath Update

Noted Committee 2 papers

Helensburgh & Lomond Area Committee noted this item on Tuesday 14 March 2023. Below is the council's own wording, with the papers it was decided on.

Item10

Resolved

Decision The Helensburgh and Lomond Area Committee:- 1. noted the agreement of five change requests from WSP at an additional cost of £28,538.97, taking the total cost of WSPs work to £253,427.96. This additional cost is covered by externally secured funding; 2. welcomed the progress made by WSP towards completing their work package by 31 March 2023; 3. noted that some elements of work will require to be completed separately during summer 2023 to finalise the full package required for construction; and 4. noted the current tender exercise for a design consultant to commence work on the section of route linking Morrisons Supermarket to Helensburgh Town Centre/Waterfront. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 13 February 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh & Lomond Area Committee

Executive summary

1.1This report updates Members on the progress made since the previous report to the Helensburgh and Lomond Area Committee on 13 December 2022 in relation to the delivery of a dedicated, high quality walking and cycle route linking Helensburgh, Cardross and Dumbarton.

1.2Officers have approved five (5) change requests from WSP, resulting in a cost increase of £28,538.97, taking the total cost of WSPs work to £253,427.96. This additional cost can be accommodated within the secured external funding.

1.3WSP have recommenced their work package and have confirmed their work will be finished no later than 31 March 2023.

1.4Subsequent to WSPs work, Officers are working to identify further elements which will require to be undertaken during summer 2023 to complete the design package required for construction. This includes ground investigation (GI) surveys, ecology surveys which can only be undertaken during summer months, a quality review of the design work undertaken by WSP and submission of planning application and related statutory permissions.

1.5Following completion of the full design package, the Council’s Estates Team will lead the land acquisition process with landowners in order to secure the land necessary to construct the designed route.

1.6While funding has been secured to complete the design stages of the project; based on current funding models, to pay for construction of the route further competitive applications will be required to a range of programmes including the Strathclyde Partnership for Transport (SPT) Capital Programme and the Transport Scotland Places for Everyone (PFE) Programme, administered by Sustrans. The PFE Programme requires a minimum of 30% of total construction costs are secured from other, non-Transport Scotland derived, sources.

1.7Officers are currently tendering for a design consultancy to identify the preferred route linking the existing cyclepath at Morrisons Supermarket/Hermitage Academy to Helensburgh Town Centre and the new section of segregated cycleway under construction at Helensburgh Waterfront, and to develop the preferred route to concept design stage. It is expected this work will commence in May 2023 and be completed in financial year 2023/24. This work is being funded via a successful competitive application to Transport Scotland’s PFE Programme.

Recommendations

1.8It is recommended that the Helensburgh and Lomond members:

1.8.1. Note the agreement of five change requests from WSP at an additional cost of £28,538.97, taking the total cost of WSPs work to £253,427.96. This additional cost is covered by externally secured funding.

1.8.2. Welcome the progress made by WSP towards completing their work package by 31 March 2023.

1.8.3. Note that some elements of work will require to be completed separately during summer 2023 to finalise the full package required for construction.

1.8.4. Note the current tender exercise for a design consultant to commence work on the section of route linking Morrisons Supermarket to Helensburgh Town Centre/Waterfront. ARGYLL AND BUTE COUNCIL Helensburgh and Lomond Area Committee DEVELOPMENT AND ECONOMIC 14 March 2023 GROWTH

Helensburgh, Cardross and Dumbarton Cyclepath Update

2.0INTRODUCTION

2.1This report updates Members of the progress made since the Helensburgh and Lomond Area Committee on 13 December 2022 in relation to the delivery of a dedicated, high quality walking and cycle route linking Helensburgh, Cardross and Dumbarton.

2.2Full details of the project, including previous progress is available in the project update reports previously presented to this Committee.

3.1It is recommended that the Helensburgh and Lomond members:

3.1.1. Note the agreement of five change requests from WSP at an additional cost of £28,538.97, taking the total cost of WSPs work to £253,427.96. This additional cost is covered by externally secured funding.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 313 KB Download
PDF
Helensburgh, Cardross and Dumbarton Cyclepath UpdateReport 225 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 12 attended
IC
Iona CampbellSecretary, expected
MC
Councillor Math Campbell-SturgessMember, apologies
MC
Councillor Maurice CorryMember, present
GH
Councillor Graham HardieMember, present
FH
Councillor Fiona HowardMember, present
MI
Councillor Mark IrvineMember, apologies
PD
Councillor Paul Donald KennedyMember, present
IM
Councillor Ian MacQuireMember, present
GM
Councillor Gary MulvaneyVice-Chair, present
IP
Councillor Iain PatersonMember, present
GP
Councillor Gemma PenfoldChair, present
JS
Julieann SmallSecretary, expected

On this subject at Argyll and Bute

Search all
  1. Helensburgh, Cardross and Dumbarton Cyclepath UpdateThis decision
  2. Helensburgh, cardross and dumbarton cyclepath progress reportApproved
  3. Helensburgh, cardross and dumbarton cyclepath progress reportAgreed
  4. Helensburgh, cardross and dumbarton cyclepath updateDecided
  5. Helensburgh, Cardross and Dumbarton Cyclepath UpdateApproved
  6. Helensburgh, Cardross and Dumbarton Cyclepath UpdateDecided

More from Argyll and Bute Helensburgh & Lomond Area Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... Noted Open
8 Sep 2026 Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... Noted Open
8 Sep 2026 Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... Noted Open
8 Sep 2026 Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... Noted Open
8 Sep 2026 Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies