HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH PROGRESS REPORT
ApprovedCommittee4 papers
AI summaryArgyll and Bute's Helensburgh and Lomond Area Committee has approved switching Phase 1 of the Helensburgh-Cardross-Dumbarton cyclepath to the south (seaward) side of the A814, and agreed to progress Phase 3 design and land acquisition.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedplus approval to appoint Phase 3 design team
Money26/27 ATIF Tier 2 bid submittedno sums specified in the report
What happens nextDesign team for Phase 3, land acquisitionsubject to suitable tender returns and funding confirmation
Who it affectsHelensburgh, Cardross and Dumbarton residents5 Phase 1 landowners, 6 Phase 2 landowners, walkers, cyclists
What was decided
The Committee approved updating the preferred alignment for Phase 1 to one primarily following the south (seaward) side of the A814, after a deliverability review of an alternative route on the inland side of the railway. Report P11, P21, 1.3, 4.8, 4.9
The Committee supported officers' efforts, subject to receiving suitable tender returns, to appoint a design team to complete development of Phase 3 designs through Developed Design and Technical Design stages. Report P12, P22, 1.6, 4.14
The Committee instructed the Council's Estates Team to prepare to rapidly progress necessary land acquisition on completion of the designs, and welcomed the continued positive engagement of landowners. Report P10, P13, P20, P23, 4.4, 4.5
Why
A deliverability review by the external design team Connected Transport Planning (CTP) found the A814 route more deliverable, maintainable and adoptable than the railway route, with broadly similar end-user benefits, and supported by the Roads and Infrastructure Service. Report 1.3, 4.8, 4.9
All five Phase 1 landowners have provisionally stated support for a route following the A814, subject to localised design considerations, which should enable faster delivery and reduce reliance on a compulsory purchase order. Report 1.4, 4.3, 4.4
What happens next
Phase 2 ground investigation work, around half complete by January 2026, is due to finish in summer 2026 once Scottish Gas Networks has located the intermediate pressure gas pipe between Ardoch and Cardross. Report 1.5, 4.13
Officers will await confirmation of 26/27 ATIF Tier 2 funding from Transport Scotland before releasing the tender for a new Phase 3 design team to take the route from concept through developed and technical design stages. Report 1.6, 1.8, 4.2, 4.14
On completion of designs the Estates Team will engage with landowners to progress land acquisition; the Roads and Infrastructure Service is preparing to adopt and maintain the path. Report 4.15, 4.19
The money
ATIF Tier 2 funding offer covering the period 01 April 2025 to 31 March 2026 25/26 funding offer from Transport Scotland, received 09 December 2025 Report 4.1
26/27 ATIF Tier 2 funding application submitted by officers, awaiting Transport Scotland confirmation Report 1.8, 4.2
Options considered
Chosen: Phase 1: route following the south (seaward) side of the A814. More deliverable, maintainable and adoptable; better landowner and stakeholder support; broadly similar end-user benefits to the railway route. Report 1.3, 4.8, 4.9
Rejected: Phase 1: route following the inland side of the railway line. Less deliverable and maintainable; less support from landowners; requires more land and higher capital costs. Report 4.9
Rejected: Designating the cyclepath for equestrian use, as requested by the British Horse Society. Transport Scotland does not consider equestrian use to be active travel so no funding can be used; legal review found no secure option under the Land Reform (Scotland) Act 2003 or the Roads (Scotland) Act 1984. Report 1.9, 4.24, 4.25, 4.27, 4.28
Implications
Financial: Design and construction are planned to be funded by external applications; the Council has not contributed to design or capital costs to date. The Council does not currently receive funding for cyclepath maintenance, an issue raised with Transport Scotland. Report 4.18
Legal: Continued input from Legal Services will be needed for contractual agreements, land acquisition and any Traffic Regulation Orders; a compulsory purchase order remains a fallback if land cannot be agreed. Report 4.22
Risk: Top project risks identified are land access, land acquisition, programme and funding; top design risks include ecological impacts near the Inner Clyde SSSI and RAMSAR site, proximity to the live railway, ground conditions, drainage and flood risk. Report 4.22, 4.23
Equalities: The route is designed to be DDA compliant and to provide an accessible route for users of mobility aids, prams and buggies, supporting protected characteristics and reducing transport poverty.
Climate: Active travel is the least carbon intensive mode; the route is expected to provide a lower-carbon alternative to private car use between Helensburgh, Cardross and Dumbarton. Report 5.1
Other: The project supports the Council's Outcomes Improvement Plan outcomes on Transport Infrastructure and Community Wellbeing, and the Scottish Government's Cycling Action Plan for Scotland and National Walking Strategy. Report 6.1
Who and where
Residents of Helensburgh, Cardross and Dumbarton and the wider Helensburgh-Cardross-Dumbarton corridor Report 1.1, 5.1
Five landowners identified on Phase 1 (Moss Road, Colgrain to Cardross) Report 4.3, 4.4
Six landowners identified on Phase 2 (Ferry Road, Cardross to Dumbarton) Report 4.3, 4.5
Walkers, cyclists, and other path users, including those with mobility aids Report 5.1
The British Horse Society, which has requested equestrian use of the cyclepath Report 1.9, 4.24
Network Rail, due to the route's proximity to a live electrified railway Report 4.23
Timeline
01 April 2025 to 31 March 2026: Period covered by the 25/26 ATIF Tier 2 funding offer Report 4.1
09 December 2025: Previous progress report considered by the Committee; 25/26 ATIF Tier 2 funding offer received from Transport Scotland Report 2.1, 4.1
10 May 2026: Report dated by the Executive Director for Development and Economic Growth Report P73
Summer 2026: Phase 2 ground investigation due to complete once SGN gas pipe is located Report 1.5, 4.13
09 June 2026: Helensburgh and Lomond Area Committee meeting Report P14, P15
Plain English for the jargon
ATIF: Active Travel Infrastructure Fund, a Transport Scotland grant programme
Cycle by Design: Transport Scotland's national design guidance for cycle infrastructure
CPO: Compulsory Purchase Order, a legal mechanism for acquiring land
CTP: Connected Transport Planning, the external design team for Phases 1 and 2
DDA: Disability Discrimination Act, referenced as the route being designed to be DDA compliant
GI: Ground Investigation, intrusive and non-intrusive surveys of ground conditions
RAMSAR: Wetland site designated under the Ramsar Convention
RIS: Roads and Infrastructure Service of Argyll and Bute Council
SGN: Scottish Gas Networks, the gas distribution network operator
SSSI: Site of Special Scientific Interest
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
Decision The Helensburgh and Lomond Area Committee: 1. welcomed the continued positive engagement of landowners; 2. approved the update of the preferred alignment for Phase 1 of the route to one primarily following the south (seaward) side of the A814; 3. supported Officer’s efforts, subject to receiving suitable tender returns, to seek to appoint a design team to complete development of Phase 3 designs through Developed Design and Technical Design stages; and 4. instructed the Council’s Estates Team to prepare to rapidly progress necessary land acquisition on completion of the designs. (Reference: Executive Director with the responsibility for Development and Economic Growth, dated 10 May 2026, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates Members on the progress made since the previous report to this Committee on 09 December 2025 in relation to the delivery of a high-quality walking and cycle route linking Helensburgh, Cardross and Dumbarton.
1.2Surveys: initial topographical, ecological and winter birds surveys have been completed for whole of Phase 1 and Phase 2.
1.3Phase 1: The external design team, Connected Transport Planning (CTP), have undertaken a deliverability review re-considering both the route adjacent to the inland side of the railway line and the historical route adjacent to the A814 road. The deliverability review has considered a range of relevant factors to identify the route option which delivers the best overall package. The review indicates that a route following the southern (seaward) side of the A814 would provide the best overall package when compared to a route following the inland side of the railway.
1.4As part of the continued efforts to progress Phase 1, Officers and the external design team have worked collaboratively have continued to meet with landowners. All landowners have indicated their support in principle for a route following the A814. Having landowner support for a single route should enable faster development and delivery of the route and reduce the likelihood of having to rely on a compulsory purchase order (CPO) to acquire land.
1.5Phase 2: Officers and CTP have continued to engage with landowners to secure their agreement to enable the essential ground investigation (GI) work to be undertaken. The ground investigation commenced in January 2026, with around half of Phase 2 now surveyed. To complete the Phase 2 GI surveys Officers and CTP have worked with Scottish Gas Networks (SGN) to conclusively locate the intermediate pressure gas pipe in the vicinity of the proposed alignment of the cyclepath on the north (inland) side of the A814 between Ardoch and Cardross. Having secured SGN agreement, it is now planned that GI work will be completed in summer 2026.
1.6Phase 3: Officers are awaiting confirmation of 26/27 funding to enable the tender for a new design team to progress the designs for Phase 3 linking Helensburgh Waterfront to Morrison’s Supermarket from the current concept stage through developed and technical stages to be released. 1.7. Funding: Transport Scotland provided an offer of 25/26 Active Travel Infrastructure Fund (ATIF) Tier 2 funding offer on 09 December 2025, covering the period 01 April 2025 to 31 March 2026.
1.8Officers have submitted a 26/27 ATIF Tier 2 funding application, as ATIF funding is only awarded for a single financial year, and are awaiting confirmation from Transport Scotland if any 26/27 ATIF Tier 2 funding will be provided for the Helensburgh, Cardross and Dumbarton Cyclepath. Officers have continued to engage with colleagues in Transport Scotland and understand the 26/27 funding offers are currently progressing through the lengthy internal Transport Scotland approval process, but not if the Helensburgh, Cardross and Dumbarton Cyclepath is to offered funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.