Decision The Helensburgh and Lomond Area Committee: 1. instructed Officers, subject to securing external funding, to seek a new design team to continue development of Phase 1 and Phase 2 designs to complete Developed Design and Technical Design stages; and 2. supported progression of the project to full Technical Design, as required by the external funder. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 17 May 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates Members on the progress made since the previous report to the Helensburgh and Lomond Area Committee on 12 March 2024 in relation to the delivery of a dedicated, high quality walking and cycle path linking Helensburgh, Cardross and Dumbarton. The delivery of this path is a stated Council Priority.
1.2Officers are reviewing the large amount of data provided by WSP following termination of their contract in March 2024 for Phase 1 (Colgrain – Cardross) and Phase 2 (Cardross – Dumbarton). This is necessary to identify the outstanding items of work which require to be completed to deliver a robust design package and to satisfy funder requirements.
1.3The Feasibility report for Helensburgh Town Centre East (Phase 3) is currently in draft form with funders for comment.
1.42024/25 funding applications have been submitted to Transport Scotland’s Places for Everyone (PFE) programme to enable design work to continue.
Recommendations
1.5It is recommended that the Helensburgh and Lomond members:
1.5.1. Instruct Officers, subject to securing external funding, to seek a new design team to continue development of Phase 1 and Phase 2 designs to complete Developed Design and Technical Design stages.
1.5.2. Support progression of the project to full Technical Design, as required by the external funder. ARGYLL AND BUTE COUNCIL HELENSBURGH AND LOMOND AREA COMMITTEE
DEVELOPMENT AND ECONOMIC 11 JUNE 2024 GROWTH
HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE
2.0INTRODUCTION
2.1This report updates Members of the progress made since the Helensburgh and Lomond Area Committee on 12 March 2024 in relation to the delivery of a dedicated, high quality walking and cycle path linking Helensburgh, Cardross and Dumbarton. The delivery of this path is a stated Council Priority.
2.2Full details of the project, including previous progress is available in the project update reports previously presented to this Committee.
3.1It is recommended that the Helensburgh and Lomond members:
3.1.1. Instruct Officers, subject to securing external funding, to seek a new design team to continue development of Phase 1 and Phase 2 designs to complete Developed Design and Technical Design stages.
3.1.2. Support progression of the project to full Technical Design, as required by the external funder.
4.0DETAIL
4.1The Council’s Active Travel Team, 1.7 FTE (Full Time Equivalent employees), is part of the Strategic Transport Team within the Development and Economic Growth Service. No Council funding is currently received by the Active Travel Team. All project costs, including internal staff costs, have to be funded via successfully securing highly competitive external challenge funds.
4.2In 2023/24 the Active Travel Team secured £2.56M external funding for the development and delivery of a total of 22 projects across Argyll and Bute, including the Helensburgh – Cardross – Dumbarton Cyclepath. This required 18 separate competitive funding applications, to 5 separate funds.
Funding
4.3Transport Scotland’s Places for Everyone (PFE) programme is the primary external active travel design funding available in Scotland. It is structured around 8 project stages with a competitive challenge fund, with the 32 local authorities, 7 regional transport partnerships, two national parks and numerous community groups across Scotland competing against each other to secure the funding each project requires.
4.4As of 2024/25, the construction element of the funding has been taken into a separate competitive fund, Transport Scotland’s Active Travel Infrastructure Fund (ATIF). ATIF still requires a separate competitive application to be submitted but is, currently, only open for applications once a year. All projects submitted to ATIF must be ready in all respects to commence construction, including having any legal or regulatory approvals required in place.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.