Decision The Helensburgh and Lomond Area Committee: 1. welcomed, subject to securing external funding, the appointment of a new design team to complete development of Phase 1 and Phase 2 designs through Developed Design and Technical Design stages; 2. instructed Officers, subject to securing external funding, to appoint a design team to complete development of Phase 3 designs through Developed Design and Technical Design stages; 3. instructed Legal Services to utilise the Council’s statutory powers as necessary to enforce access to private land for surveys required as part of the design process where landowner permission is not forthcoming; 4. agreed to work to identify potential sources of construction match funding, estimated to require a minimum of £3M to complete the route; and 5. instructed Roads and Infrastructure Service to adopt all sections of the Helensburgh – Cardross – Dumbarton Cyclepath once constructed including those not contiguous with an adopted road, and maintain as part of the Council Roads Asset Management Plan (RAMP). (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 3 February 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
1.1This report updates Members on the progress made since the previous report to this Committee on 10 September 2024 in relation to the delivery of a high quality walking and cycle route linking Helensburgh, Cardross and Dumbarton.
1.2Phase 1 & 2: Officers worked with Procurement colleagues undertake a procurement exercise for a new design team to complete the Developed Design (Stage 3) and Technical Design (Stage 4) covering Phase 1 (Colgrain – Cardross) and Phase 2 (Cardross – Dumbarton). This is necessary to complete the outstanding items of work which are required to deliver a robust design package and to satisfy funder requirements.
1.3Phase 1 & 2: Following a competitive open tender process via Public Contracts Scotland, the preferred tenderer was identified as Connected Transport Planning (CTP). Due to funding restrictions, a contract was awarded to CTP covering February and March 2025 to enable initial progress on continuing the Developed design stage to be made. Subject to securing appropriate funding, the procurement has been structured to allow a contract to be directly award to CTP for 2025/26 to continue the Developed and Technical design stages.
1.4Phase 3: Civic Engineers (CE) have continued to developed the Concept Design for Phase 3 of the project as part of the Helensburgh Town Centre East (Helensburgh in Motion) project. It is programmed that the Concept Design work will be completed by late March 2025 in line with the funders requirements.
1.5Phase 3: A community consultation was held between 23 November 2024 to 05 January 2025. Information material and the survey were available on-line via the Council’s website for the 6-week period, with posters and flyers distributed to local shops, library and churches. The consultation was also promoted via appropriate social media channels. Two in-person events were held, at the Hermitage Academy Christmas Fair on 23 November and at the Helensburgh and Lomond Civic Centre on 16 December. Officers and the design team also attended the Helensburgh Community Council meeting on 28 November 2024.
1.6The consultation received a total of 185 responses; with 59% (105) not feeling safe travelling actively on the A814 at present; 85% (154) believing that improvements to the area would make people more likely to walk, wheel or cycle; 79% (143) requested improved cycling infrastructure, 61% (11) more or safer crossing points and 49% (89) traffic calming measures. 1.7. In 2024/25 Officers secured a total of £150,000 from Transport Scotland’s Places for Everyone (PFE) programme, administered by Sustrans, to enable progress to be made in relation to all phases of the design.
1.8Internally, Officers continue to seek guidance from Legal Services on the use of the Council’s statutory powers to enforce access to private land for the necessary surveys (e.g. ecology or ground investigation) where landowner permission is not forthcoming. Officers also continue to seek engagement with colleagues in Legal Services to seek to progress approval from Council to develop a CPO for the remaining sections of this important route.
Recommendations
1.9It is recommended that the Helensburgh and Lomond members:
1.9.1. Welcome, subject to securing external funding, the appointment a new design team to complete development of Phase 1 and Phase 2 designs through Developed Design and Technical Design stages.
1.9.2. Instruct Officers, subject to securing external funding, to appoint a design team to complete development of Phase 3 designs through Developed Design and Technical Design stages.
1.9.3. Instruct Legal Services to utilise the Council’s statutory powers as necessary to enforce access to private land for surveys required as part of the design process where landowner permission is not forthcoming.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Helensburgh & Lomond Area Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref...
Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.