Resolved
Decision The Environment, Development and Infrastructure Committee endorsed the programme of bridge works. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated April 2023, submitted)
Environment, Development and Infrastructure Committee decided this item on Thursday 1 June 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision The Environment, Development and Infrastructure Committee endorsed the programme of bridge works. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated April 2023, submitted)
2.1It is recommended that Members of the Environment, Development and Infrastructure Committee endorse the programme of bridge works.
3.0DETAIL
3.1The fund will be used to undertake proportionate works (from strengthening to comply with ‘construction and use’ weight limits to full off-line rebuilds) on bridges in need of repair, identified through our inspection programme/ records. Bridges provide critical transport (often lifeline) connections for some communities and are a vital part of the wider road network.
3.2The table below details the list of bridges which have received funding along with indicative key dates.
Estimated Grant Site Start Bridge Name Completion Amount Date Date 1 B840-140 Archonnell Bridge £40,000 Sep 23 Jan 24 2 B842-010 Claonaig Bridge £477,000 Jan 24 May 24 3 A815-230 Cothouse Bridge £517,000 Aug 23 Jun 24 4 A846-270 Glenegedale (2) £597,000 Jun 24 Dec 24 5 B844-010 Kilninver Bridge £1,194,000 Aug 24 Aug 25 6 B839-050 Lochgoilhead Bridge £198,000 Apr 24 Mar 25 7 A816-120 Oude £1,194,000 Mar 25 Aug 26 8 A849-280 Pennyghael Bridge £1,193,000 Aug 24 Jul 26 9 B842-150 Whitestone Bridge £40,000 Nov 23 Mar 24 Total £5,450,000
3.3Location plans for each bridge in the table above are in Appendix 1. Regular updates on these works as they progress will be provided through our weekly members briefing.
3.4Description of the works proposed:
3.4.1 - B840-140 Archonnell Bridge Additional retaining buttress structure constructed on downstream face of existing bridge.
3.4.2 - B842-010 Claonaig Bridge Strengthening of wing walls, realignment of road, waterproofing, and drainage works.
3.4.3 - A815-230 Cothouse Bridge Installation of deck waterproofing system (under road surface), installation of new expansion joints, joint sealings, concrete repair works, drainage works, vehicle barrier partial replacement, vegetation removal
3.4.4 - A846-270 Glenegedale (2) Full bridge replacement (with footway) in same location.
3.4.5 - B844-010 Kilninver Bridge Full bridge replacement (with footway). Options Appraisal Report (due shortly) shall determine preferred alignment.
3.4.6 - B839-050 Lochgoilhead Bridge Strengthening of arch barrel, including waterproofing, temporary traffic diversion and drainage works.
3.4.7 - A816-120 Oude Full bridge replacement (with footway) upstream / northwards. Options Appraisal Report (due shortly) shall determine preferred alignment.
3.4.8 - A849-280 Pennyghael Bridge Full bridge replacement (with footway) downstream / seawards. Options Appraisal Report (due shortly) shall determine preferred alignment.
3.4.9 - B842-150 Whitestone Bridge Additional retaining buttress structure constructed on downstream face of existing bridge.
3.5Legislation, Standards, Codes of Practice: Replacement (new) structures are designed in accordance with: Roads (Scotland) Act 1984 Legislation Design Manual for Roads and Bridges (DMRB) document “CD 350 - The design of highway structures” and associated document series “Highway Structures & Bridges” “CIHT 'Well-managed highway infrastructure' Code of Practice” Section C6 and associated documentation.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
BRIDGE LOCATION PLANSAppendix 1 | 13 MB | Download |
PDF |
LOCAL BRIDGE MAINTENANCE FUNDReport | 225 KB | DownloadRead as text |
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Oct 2026 | A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... | Noted | Open |
| 9 Oct 2026 | Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... | Noted | Open |
| 9 Oct 2026 | Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... | Noted | Open |
| 9 Oct 2026 | Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... | Approved | Open |
| 9 Oct 2026 | Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.