Decision The Environment, Development and Infrastructure Committee – 1. endorsed the content of the submitted report; and 2. noted that further updates would be provided for the Environment, Development and Infrastructure Committee on 31 August 2023. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated 1 June 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The Council has in place a 25 year Waste PPP contract with Renewi which ends in September 2026. The waste PPP contract covers Oban and Lorn, Mid Argyll and Kintyre, Bute and Cowal together with the inner islands. The contract provides a disposal solution for general waste through a Mechanical Biological Treatment (MBT) process, with residual waste being landfilled. The contract also provides a transfer facility and haulage for co- mingled recycling.
1.2Scottish Government are due to introduce a Biodegradable Municipal Waste (BMW) landfill ban from the end of December 2025. The last 9 months of the PPP 25 year contract will not be compliant with the new regulation.
1.3This report provides the Environment, Development and Infrastructure Committee (ED&I) with an update on the Waste PPP, and information relating to the continuation of engagement with Scottish Government regarding the derogation. Further discussion is taking place with Renewi as part of the considerations of the options appraisal (options noted below) reported to ED&I in December 2022.
Recommendations
It is recommended that the Environment, Development and Infrastructure Committee:-
Consider and endorse the content of this report and that further updates will be provided for September ED&I Committee. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT & INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE SERVICES 1 JUNE 2023
WASTE PPP UPDATE
2.0INTRODUCTION
2.1This report provides an update on Waste projects and engagement taking place with Scottish Government and Renewi following report presented to ED&I committee on 1st December 2022.
3.0RECOMMENDATIONS 3.1 Consider and endorse the content of this report and that further updates will be provided for September ED&I Committee.
4.0DETAIL 4.1 The December ED&I report recommended two options for pursuance which are noted below and being progressed by Officers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.