CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council
Helensburgh & Lomond Area Committee, Tuesday 13 June 2023 at 9.30am

HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATE

Noted Committee 2 papers

Helensburgh & Lomond Area Committee noted this item on Tuesday 13 June 2023. Below is the council's own wording, with the papers it was decided on.

Item15

Resolved

Decision The Helensburgh and Lomond Area Committee: 1. noted the agreement of one change requests from WSP at an additional cost of £6,479.51, taking the total cost of WSPs work to £259,907.47 and that this additional cost is covered by externally secured funding; 2. noted the amended completion date submitted by WSP of end-July 2023; 3. noted that some elements of work would require to be completed separately following completion of WSPs work to finalise the full package required for construction; 4. welcomed the progress towards the award of contract for the section of route linking Morrisons Supermarket/Hermitage Academy to Helensburgh Town Centre/Waterfront, and development of this to Concept Design stage; 5. noted appendix 1 in the paper with projected compulsory purchase orders in 2026/27, 2028/29, and 2029/30 at various phases of the scheme; and 6. agreed that officers would bring forward a report to the next Area Committee outlining: a. a quantification of the projects risks; and b. options for next steps including bringing forward compulsory purchase orders to expedite construction of the Helensburgh to Cardross phase. (Reference: Report by Executive Director with responsibility for Development and Economic Growth, dated 27 April 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Helensburgh & Lomond Area Committee

Executive summary

1.1This report updates Members on the progress made since the previous report to the Helensburgh and Lomond Area Committee on 14 March 2023 in relation to the delivery of a dedicated, high quality walking and cycle path linking Helensburgh, Cardross and Dumbarton. The delivery of this path is a stated Council Priority.

1.2Officers have approved one (1) change request from WSP, resulting in a cost increase of £6,479.51 taking the total cost of WSPs work to £259,907.47. This additional cost can be accommodated within the secured external funding from Transport Scotland’s Places for Everyone (PFE) Programme, administered by Sustrans, and Strathclyde Partnership for Transport’s (SPT) Capital Programme.

1.3WSP did not complete their work package by the previously agreed deadline of 31 March 2023. WSP have submitted an updated programme and, subject to agreement, now expect to complete their work for end-July 2023. This timescale is dependent on securing landowner agreement to enable survey access and on continued positive engagement with other key stakeholders.

1.4In March 2023, WSP sent land access requests for the purpose of non-invasive ecology surveys to the 15 affected landowners. Of these, 7 have agreed to allow access, 3 rejected the request but asked for direct contact from the Council, 3 rejected the request for access, and, at time of writing, WSP were unable to reach 2 landowners. The primary reasons for rejection of access appear to be around a loss of trust in WSP and the wider design process, exacerbated by the delay in providing feedback to landowners following initial meetings caused by the nearly 18 month pause in work by WSP. One landowner stating they opposed the selected route alignment and any proposals to cross their land, while another stated that the path crossing their land was not part of their revised business plan. The responses clearly indicate the need for the design team and the wider project to seek to rebuild trust with landowners if we are to progress this project in a cooperative approach.

1.5Subsequent to WSPs work, Officers are working to identify further elements which will require to be undertaken following completion of WSPs work to complete the design package required for construction. This includes ground investigation (GI) surveys, ecology surveys which can only be undertaken during summer months, a quality review of the design work undertaken by WSP and submission of planning application and related statutory permissions.

1.6Following completion of the full design package, the Council’s Estates Team will lead the land acquisition process with landowners in order to secure the land necessary to construct the designed route.

1.7Officers are working to award a contract to a design contractor by end-June to identify the preferred route linking the existing cyclepath at Morrisons Supermarket / Hermitage Academy to Helensburgh Town Centre and the new section of segregated cycleway under construction at Helensburgh Waterfront, and to develop the preferred route to concept design stage. The outline programme for this work forecasts completion of design stages 0-2 (Feasibility, Route Alignment and Concept Design) by the end of 2023/24. This work is being funded via successful competitive applications to SPT’s Capital Programme and Transport Scotland’s PFE Programme.

1.8While funding has been secured to complete the design stages of the project; based on current funding models, to pay for construction of the route further competitive applications will be required to a range of programmes including the SPT Capital Programme and the Transport Scotland PFE Programme. The PFE Programme requires a minimum of 30% of total construction costs are secured from non-Transport Scotland derived sources.

Recommendations

1.9It is recommended that the Helensburgh and Lomond members:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20230613 HL Area Committee Cardross Cyclepath Update Report: Appendix 1 Programme of WorkAppendix 306 KB Download
PDF
20230613 HL Area Committee H-C-D Cyclepath Update ReportReport 236 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
IC
Iona CampbellSecretary, expected
MC
Councillor Math Campbell-SturgessMember, present
MC
Councillor Maurice CorryMember, present
GH
Councillor Graham HardieMember, present
FH
Councillor Fiona HowardMember, present
MI
Councillor Mark IrvineMember, apologies
PD
Councillor Paul Donald KennedyMember, present
IM
Councillor Ian MacQuireMember, present
GM
Councillor Gary MulvaneyVice-Chair, present
IP
Councillor Iain PatersonMember, present
GP
Councillor Gemma PenfoldChair, present
JS
Julieann SmallSecretary, expected

On this subject at Argyll and Bute

Search all
  1. HELENSBURGH, CARDROSS AND DUMBARTON CYCLEPATH UPDATEThis decision
  2. Helensburgh, cardross and dumbarton cyclepath progress reportApproved
  3. Helensburgh, cardross and dumbarton cyclepath progress reportAgreed
  4. Helensburgh, cardross and dumbarton cyclepath updateDecided
  5. Helensburgh, Cardross and Dumbarton Cyclepath UpdateApproved
  6. Helensburgh, Cardross and Dumbarton Cyclepath UpdateDecided

More from Argyll and Bute Helensburgh & Lomond Area Committee

All decisions
MeetingDecisionOutcome
8 Sep 2026 Police scotland updateDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Report by Police Scotl... Noted Open
8 Sep 2026 Clyde transformation programme & clyde land acquisition overviewDecision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Verbal update from Cly... Noted Open
8 Sep 2026 Charts (argyll and the isles)Decision The Helensburgh and Lomond Area Committee noted the information provided. (Reference: Presentation by Chair,... Noted Open
8 Sep 2026 Area performance report - fq1 2026/27Decision The Helensburgh and Lomond Area Committee noted the performance and supporting commentary as presented. (Ref... Noted Open
8 Sep 2026 Supporting communities fund 2026/27Decision The Helensburgh and Lomond Area Committee agreed that the 18 applications, marked as Award’ and ‘Partial Awa... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies