Decision The Environment, Development and Infrastructure Committee – 1. approved the 2023/24 Winter Service Policy Document at Appendix 1 to the submitted report; 2. approved the Salt Use Reduction and Preservation of Stocks Protocol at Appendix 2 to the submitted report; 3. noted Appendices 3 – 6 of the submitted report; and 4. noted that a review of the financial position was being carried out and this would be reported to the Policy and Resources Committee in October. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated August 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1Each year Members consider for approval, the Council’s Winter Service Policy. The format and general content of the Winter Service Policy 2023/24 remains similar to that of the 2022/23 Policy.
1.2The policy sets out priorities for treatment and routes, which will be ‘pre- treated’ in advance of winter hazards. In prolonged winter conditions, the policy provides for all roads to be treated, with resources being allocated to focus on the hierarchy of priorities (i.e. the lower priorities will only be cleared once the higher priorities have been treated and remain clear of any recurring hazards).
1.3The policy is a comprehensive document setting out the management, governance and operational requirements for the winter service. The policy sets out signing provision to warn the travelling public of roads which are unsuitable for use during extreme winter conditions. The policy also provides a protocol for the reduction in use of salt and preservation of remaining stocks in the event of salt stock replenishment operations being disrupted. This was introduced following the severe winters of 2009/10 and 2010/11 when national salt supplies were interrupted.
Recommendations
It is recommended that the Environment, Development and Infrastructure Committee:-
Approves the 2023/24 Winter Service Policy Document at Appendix 1. Approves the Salt Use Reduction and Preservation of Stocks Protocol at Appendix 2. Notes Appendices 3 – 6 of this report. Note that a review of the financial position is being carried out and this will be reported to the Policy and Resources Committee in October. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE SERVICES 31 AUGUST 2023
WINTER SERVICE POLICY 2023/24
2.0INTRODUCTION
2.1This report presents the Winter Service Policy 2023/24 which remains in a similar format and covers a similar network to the Policy approved by this Committee in previous years. This generally remains based on the network and times of the public bus service with additional priority and resources allocated to strategic high speed roads.
3.1It is recommended that the Environment, Development and Infrastructure Committee:-
Approves the 2023/24 Winter Service Policy Document at Appendix 1. Approves the Salt Use Reduction and Preservation of Stocks Protocol at Appendix 2. Notes the Appendices 3 – 6 of this report. Note that a review of the financial position is being carried out and this will be reported to the Policy and Resources Committee in October.
4.0DETAIL
Winter Service Policy 2023/24
4.1The proposed Winter Service Policy for 2023/24 at Appendix 1, in terms of treatment standards and routes, remains unchanged from last year.
4.2There have however, been a number of minor operational changes in the past 12 months which are:-
A new Weather Forecast Service Contract Provider has been appointed, this being a joint procurement with several Councils across the West of Scotland. An operational adjustment was made to Lorn pre-treatment routes with a seventh route “L7-Lorn Arc Bus Routes” introduced prior to operations commencing in November 2022.
Following the new Generation 6 (G6) trunk road contract for the north west region which has been awarded by Transport Scotland to BEAR Scotland the sub contract services previously provided by the Council for winter and reactive out of hours call outs on the trunk road in Kintyre, since August 2014 when the southern section of the A83 was trunked, will now be delivered directly by BEAR who no longer require the services of the Council. A review of the Kintyre local road network routes will now be part of the assessment of overall capability, in the run up to the Winter Service period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.