Decision The Environment, Development and Infrastructure Committee – 1. noted the current progress contained within the submitted report; and 2. agreed to recognise the contribution and to reflect on the role played by third sector groups, taking a local lead in respect of the Animation of Rothesay Castle, which was implemented in collaboration with Bute Island Improvement District and the pop-up shop in the former Clydesdale Bank, and to note that this success had been driven by Bute Island Alliance Scottish Charitable Incorporated Organisation. (Reference: Report by Executive Director with responsibility for Development and Economic Growth dated July 2023, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Executive summary
1.1The purpose of this report is to update the Environment, Development and Infrastructure Committee on progress of the large-scale, externally funded project work of the Transformational Projects and Regeneration Team, and to highlight key issues that may impact on the successful delivery of projects.
1.2The last update report was considered by Environment, Development and Infrastructure Committee in March 2023.
1.3The team is currently responsible for the delivery and or management of projects and or associated grants with a cumulative value of over £42m. Projects and or associated grants the team manages are listed in Appendix A. It should be noted that following completion of each project the team continues to have the responsibility for the monitoring and final drawdown and reporting up until the end of the 12-month defects period or beyond depending on conditions on the respective grant contracts.
Recommendations
It is recommended that the Environment, Development and Infrastructure Committee consider and note the current progress contained within the report. ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
DEVELOPMENT AND ECONOMIC 31 AUGUST 2023 GROWTH
TRANSFORMATIONAL PROJECTS AND REGENERATION TEAM – LARGE SCALE PROJECT UPDATE REPORT
2. INTRODUCTION
2.1This report sets out the current position of the large-scale projects, which are currently being delivered by the team and or where Council and externally secured grants are being managed by the Transformational Projects and Regeneration Team.
2.2The Transformational Projects and Regeneration Team sits within the Council’s Development and Economic Growth Service and works region-wide. The team has a particular focus on ‘place’, heritage regeneration, the creative industries, renewables and Islands and works closely with colleagues across the Council, communities, third sector organisations, town centre heritage building owners and businesses to realise positive change.
2.3The team’s work broadly includes the following areas:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.