Decision The Argyll and Bute Harbour Board – 1. noted the update on the major programmes currently being addressed within the Argyll and Bute Council’s Marine Asset Management Plan; 2. noted that £28.75 million worth of capital works were underway or were about to commence in the financial year 2024 / 2025; 3. noted that there was a potential spend of c. £129 million over the next 5 years, the majority of which would support the new CMAL & CFL / CalMac fleet renewal; and 4. approved the award of £15 million works for the Iona breakwater project. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated February 2024, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
2.1Members are asked to: 2.1.1 Consider the update on the major programmes currently being addressed within the Argyll and Bute Council’s Marine Asset Management Plan. 2.1.2 Note that £28.75 million worth of capital works are underway or about to commence in the financial year 2024 / 2025. 2.1.3 Note that there is a potential spend of c. £129 million over the next 5 years, the majority of which will support the new CMAL & CFL / CalMac fleet renewal. 2.1.4 Approve the award of the £15 million works for Iona breakwater project.
3.0DETAIL
3.1.1 Funding for Piers & Harbours is mainly provided by Prudential borrowing paid back through fees and charges, however external funding can also be sourced through capital grants, shared cost agreements and funds made available for specific projects. The Marine Asset Management Plan is an adaptable plan fed into by changing priorities and circumstances. It also relies on steady and predictable income from those ferry services utilising Argyll & Bute Council infrastructure to repay loan charges. Costs will be best estimated and closely watched for best value. Rising prices and availability of resources are risks which will need to be monitored in each of the projects and forecasts adjusted accordingly.
3.2Marine Services are presently engaged in a number of long and shorter term projects and works across Argyll & Bute which include: 3.2.1 Craignure – New Ferry Terminal Following advice from the Scottish Government’s Marine Directorate we have unfortunately had to stand down our ground investigation (GI) contractor until the spring. The GI works have been awarded to DUNHELM Geotechnical & Environmental Ltd with an initial plan to start on site 24th August last year for around 4 weeks. We do not anticipate that our works proposals will change through this extra process. Our priority remains getting through the licence process as quickly and efficiently as possible and having everything in place for these important works to go ahead. A timeline is being developed around some assumptions on the scale of construction for each option and location. Following extended local consultation and input, the potential issue of consensus between Craignure Community, CFL and the wider Mull and Iona views on scale will require a resolution when the GI works are completed Costs are estimated at £3M over the next two years, to reach construction which includes Ground Investigation, Licencing, completion of business cases, Environmental Impact Assessments, design and tendering.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.