Decision The Environment, Development and Infrastructure Committee noted the updates on the current position of the projects. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated 26 February 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE
ROAD AND INFRASTRUCTURE 20 MARCH 2025 SERVICES
OCTOBER 2023 WEATHER EVENT UPDATE
1.0INTRODUCTION
1.1This is a follow up to the report presented to the Policy and Resources Committee on 5 December 2024 in respect of the October 2023 weather event.
Policy and Resources Committee - October 2023 Weather Event (Item 9)
2.0RECOMMENDATIONS 2.1 It is recommended that the Environment, Development and Infrastructure Committee: -
a. Notes the updates on the current position of the projects.
3.0DETAIL 3.1 The table overleaf summarises the current status of the infrastructure repair and reconstruction projects arising from the weather event in October 2023 as at February 2025. Those works coloured green are complete. Update on Works Progress, Scheduled Completion & Estimated Total Costs
LOCATION ONGOING SCHEDULED ESTIMATED TOTAL WORKS/PROGRESS COMPLETION COSTS UPDATE
A816-110 Upstream training walls, Majority of works £200k (revenue) Cuilfail Hotel bridge parapets, completed by January £2.086m (capital) Bridge, pedestrian walkway, 2025. - NO CHANGE Kilmelford scour protection and upstream debris barrier Parapet copes due for works largely completed completion Spring 2025. November 2024. Upstream north training Some final work required wall works expected to in Spring 2025 due to be completed in SEPA delays and Summer 2025 changed advice received (previously anticipated in final week of in-water to be Spring). works, additional SEPA Licencing now required.
No additional costs identified at this stage. B844-010 Phase 1 works Phase 1 – October 2023 £180k (revenue) – Kilninver completed October - WORKS COMPLETED Bridge 2023. Phase 1
B844-010 Designs for Phase 2 Phase 2 - Late Summer Phase 2 works being Kilninver works being carried out 2026 incorporated into Bridge in-house with a view to - NO CHANGE Bridge Replacement Phase 2 works being tendered scheme already mid 2025. funded - NO CHANGE Any risks incurred from the delays to the Phase 2 works are being monitored and controlled to ensure the road network remains safe. C30 Ford to Works completed and July 2024 £864k (revenue) Malevich road fully reopened. - NO CHANGE - NO CHANGE - WORKS COMPLETED - FINAL COSTS B836-060 Further to significant Programmed for £1.150m (revenue) Balliemore delays and additional completion Spring 2025 £1.448m (capital) Bridge, Glen costs incurred from - NO CHANGE - NO CHANGE Lean diversion of OpenReach It is anticipated that apparatus within there may be some damaged bridge, increases in cost on demolition of the existing this project but these bridge is ongoing – due have been accounted to be completed late for within the wider 2024. bridge strengthening programme with New bridge construction budget confirmed as planned early 2025. available to support these costs. A816 Bealach Initial response including February 2024 £2.285m (revenue) Mor, Kintraw, clearance and quarry - WORKS COMPLETED - NO CHANGE Ardfern Works works. to February Further clearance and 2024 scaling/stabilisation works Construction of Bypass and Loop road. A816 Bealach Stability, drainage and September 2024 £1.995m (revenue) Mor, Kintraw, safety works. - WORKS COMPLETED - NO CHANGE Ardfern Works March to Standing by and ongoing September maintenance. 2024 Traffic management to September.
Contractor Project Management Costs A816 Bealach Ongoing works to Bypass road works £220k (revenue) Mor, Kintraw, bypass road continue for programmed for - NO CHANGE Ardfern Works vehicle safety barrier, completion by to edge markers. March 2025 (previously anticipated to be Monitoring of Kintraw December 2024) hillside in place to manage movement of traffic onto bypass route when necessary.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.