CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Argyll and Bute Council

OCTOBER 2023 WEATHER EVENT UPDATE

Noted Committee 1 paper

Environment, Development and Infrastructure Committee noted this item on Thursday 20 March 2025. Below is the council's own wording, with the papers it was decided on.

Item16

Resolved

Decision The Environment, Development and Infrastructure Committee noted the updates on the current position of the projects. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated 26 February 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Environment, Development and Infrastructure Committee

ARGYLL AND BUTE COUNCIL ENVIRONMENT, DEVELOPMENT AND INFRASTRUCTURE COMMITTEE

ROAD AND INFRASTRUCTURE 20 MARCH 2025 SERVICES

OCTOBER 2023 WEATHER EVENT UPDATE

1.0INTRODUCTION

1.1This is a follow up to the report presented to the Policy and Resources Committee on 5 December 2024 in respect of the October 2023 weather event.

Policy and Resources Committee - October 2023 Weather Event (Item 9)

2.0RECOMMENDATIONS 2.1 It is recommended that the Environment, Development and Infrastructure Committee: -

a. Notes the updates on the current position of the projects.

3.0DETAIL 3.1 The table overleaf summarises the current status of the infrastructure repair and reconstruction projects arising from the weather event in October 2023 as at February 2025. Those works coloured green are complete. Update on Works Progress, Scheduled Completion & Estimated Total Costs

LOCATION ONGOING SCHEDULED ESTIMATED TOTAL WORKS/PROGRESS COMPLETION COSTS UPDATE

A816-110 Upstream training walls, Majority of works £200k (revenue) Cuilfail Hotel bridge parapets, completed by January £2.086m (capital) Bridge, pedestrian walkway, 2025. - NO CHANGE Kilmelford scour protection and upstream debris barrier Parapet copes due for works largely completed completion Spring 2025. November 2024. Upstream north training Some final work required wall works expected to in Spring 2025 due to be completed in SEPA delays and Summer 2025 changed advice received (previously anticipated in final week of in-water to be Spring). works, additional SEPA Licencing now required.

No additional costs identified at this stage. B844-010 Phase 1 works Phase 1 – October 2023 £180k (revenue) – Kilninver completed October - WORKS COMPLETED Bridge 2023. Phase 1

B844-010 Designs for Phase 2 Phase 2 - Late Summer Phase 2 works being Kilninver works being carried out 2026 incorporated into Bridge in-house with a view to - NO CHANGE Bridge Replacement Phase 2 works being tendered scheme already mid 2025. funded - NO CHANGE Any risks incurred from the delays to the Phase 2 works are being monitored and controlled to ensure the road network remains safe. C30 Ford to Works completed and July 2024 £864k (revenue) Malevich road fully reopened. - NO CHANGE - NO CHANGE - WORKS COMPLETED - FINAL COSTS B836-060 Further to significant Programmed for £1.150m (revenue) Balliemore delays and additional completion Spring 2025 £1.448m (capital) Bridge, Glen costs incurred from - NO CHANGE - NO CHANGE Lean diversion of OpenReach It is anticipated that apparatus within there may be some damaged bridge, increases in cost on demolition of the existing this project but these bridge is ongoing – due have been accounted to be completed late for within the wider 2024. bridge strengthening programme with New bridge construction budget confirmed as planned early 2025. available to support these costs. A816 Bealach Initial response including February 2024 £2.285m (revenue) Mor, Kintraw, clearance and quarry - WORKS COMPLETED - NO CHANGE Ardfern Works works. to February Further clearance and 2024 scaling/stabilisation works Construction of Bypass and Loop road. A816 Bealach Stability, drainage and September 2024 £1.995m (revenue) Mor, Kintraw, safety works. - WORKS COMPLETED - NO CHANGE Ardfern Works March to Standing by and ongoing September maintenance. 2024 Traffic management to September.

Contractor Project Management Costs A816 Bealach Ongoing works to Bypass road works £220k (revenue) Mor, Kintraw, bypass road continue for programmed for - NO CHANGE Ardfern Works vehicle safety barrier, completion by to edge markers. March 2025 (previously anticipated to be Monitoring of Kintraw December 2024) hillside in place to manage movement of traffic onto bypass route when necessary.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
OCTOBER 2023 WEATHER EVENT UPDATEReport 118 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 20 attended
KS
Kate ShawCouncil Staff, expected
KM
Katie McKenzieSecretary, expected
HM
Hazel MacInnesSecretary, expected
FM
Fiona McCallumSecretary, expected
JA
Councillor John ArmourChair, present
JB
Councillor Jan BrownMember, absent
GH
Councillor Graham HardieMember, present
WH
Councillor Willie HumeMember, present
AK
Councillor Andrew KainMember, present
JL
Councillor Jim LynchMember, present
TM
Councillor Tommy MacPhersonMember, present
IM
Councillor Ian MacQuireMember, present

All 20 on the meeting page

On this subject at Argyll and Bute

Search all
  1. OCTOBER 2023 WEATHER EVENT UPDATEThis decision
  2. October 2023 weather event - november 2024 updateNoted
  3. October 2023 weather event - updateNoted
  4. October 2023 weather event - updateNoted
  5. October 2023 weather event - updateNoted

More from Argyll and Bute Environment, Development and Infrastructure Committee

All decisions
MeetingDecisionOutcome
9 Oct 2026 A816 bealach mor permanent solution updateDecision The Environment, Development and Infrastructure Committee noted the following key points – 1. the £1.1m appr... Noted Open
9 Oct 2026 Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re... Noted Open
9 Oct 2026 Review of roads and infrastructure services updateDecision The Environment, Development and Infrastructure Committee – 1. noted the progress to date on the RIS Review;... Noted Open
9 Oct 2026 Winter service policy 2026/27Decision The Environment, Development and Infrastructure Committee – 1. approved the 2026/27 Winter Maintenance Polic... Approved Open
9 Oct 2026 Waste management updateDecision The Environment, Development and Infrastructure Committee noted the content of the report. (Reference: Repor... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies