MARINE ASSET MANAGEMENT PLAN - CRAIGNURE FERRY TERMINAL

Noted Committee 3 papers

Argyll and Bute Harbour Board noted this item on Thursday 20 March 2025. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

Decision The Argyll and Bute Harbour Board – 1. considered and discussed the update on the new ferry terminal project at Craignure in conjunction with the Project Forecast attached at appendix 1 of the report; 2. noted that c.£96 million was the high-level construction projection estimate at present based on inflationary increases to the 2020 estimates; 3. approved the continuation of the project to the next phase of the project with the option referred to as option ‘D1’ as the preferred option; and 4. approved the advisory and consultation structure at 3.5 of the report and described in the terms of reference for the Working Group, consisting of Working Group and Reference Group to advise Council Officers and Elected Members. Reference: Report by Executive Director with responsibility for Roads and Infrastructure dated February 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting. Source: www.argyll-bute.gov.uk

Follow this further

Built from Argyll and Bute's papers

What the report saysPro

Report to Argyll and Bute Harbour Board

Recommendations

2.1Members are asked to: 2.1.1 Consider and discuss this update on the new ferry terminal project at Craignure in conjunction with the Project Forecast (appendix 1). 2.1.2 Note that c.£96 million is the high-level construction projection estimate at present based on inflationary increases to the 2020 estimates. 2.1.3 Approve the continuation of the project to the next phase of the project with the option referred to as option ‘D1’ (image 1) as the preferred option. 2.1.4 Approve the advisory and consultation structure at 3.5 and described in the terms of reference for the Working Group (appendix 2), consisting of Working Group and Reference Group to advise Council Officers and Elected Members.

3.0DETAIL

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Craignure OBC: project forecast update Feb 2025Appendix 1 58 KB Download
PDF
CPDWG TOR (1)Appendix 2 201 KB Download
PDF
MARINE ASSET MANAGEMENT PLAN: CRAIGNURE FERRY TERMINALReport 661 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
KS
Kate ShawCouncil Staff, expected
KM
Katie McKenzieSecretary, expected
JA
Councillor John ArmourVice-Chair, present
GB
Councillor Gordon BlairMember, apologies
MC
Councillor Maurice CorryMember, present
AK
Councillor Andrew KainMember, present
LM
Councillor Liz McCabeMember, apologies
DM
Councillor Dougie McFadzeanMember, present
RM
Councillor Ross MorelandChair, present
AV
Councillor Andrew VennardMember, present
HM
Hazel MacInnesSecretary, expected

On this subject at Argyll and Bute

Search all
  1. MARINE ASSET MANAGEMENT PLAN - CRAIGNURE FERRY TERMINALThis decision
  2. Piers and harbours marine asset management plan - works updateNoted
  3. Piers and harbours marine asset management plan fees and charges 2027 / 2028Noted
  4. Piers and harbours marine asset management plan - works updateNoted
  5. Piers and harbours - marine asset management plan - works updateNoted
  6. Piers and harbours - marine asset management plan fees & charges 2026 / 2027Agreed

More from Argyll and Bute Argyll and Bute Harbour Board

All decisions
MeetingDecisionOutcome
9 Oct 2026 Piers and harbours marine asset management plan - works updateDecision The Argyll and Bute Harbour Board noted the updates on capital works currently being progressed within the M... Noted Open
9 Oct 2026 Piers and harbours - performance reportingDecision The Argyll and Bute Harbour Board – 1. agreed the proposed approach and structure to annual performance repo... Agreed Open
9 Oct 2026 Carradale harbourDecision The Argyll and Bute Harbour Board noted the content of the report. (Reference: Report by Executive Director ... Noted Open
9 Oct 2026 Piers and harbours marine asset management plan fees and charges 2027 / 2028Decision The Argyll and Bute Harbour Board – 1. noted that officers were of the view that a review is required to con... Noted Open
9 Oct 2026 Argyll and bute harbour board workplanDecision The Argyll and Bute Harbour Board noted the content of the workplan. (Reference: Argyll and Bute Harbour Boa... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies