MARINE OPERATIONS: COUNCIL FERRY SERVICE: HITRANS GRANT
AgreedCommittee1 paper
Environment, Development and Infrastructure Committee agreed this item on Thursday 19 June 2025. Below is the council's own wording, with the papers it was decided on.
Decision The Environment, Development and Infrastructure Committee – 1. agreed that funds be allocated as follows:- i. engage with suitable contractors to realise on-site accommodation at Port Askaig ; ii. to engage with suitable Naval Architects to develop a ‘keel ready’ concept design for the Eilean Dhiura replacement ferry; and iii. to engage with suitable consultants to update and progress plans for the Cuan ferry infrastructure for use by the Eilean Dhiura and Belnahua vessels; and 2. in the event that part of the grant remains, approved ringfencing the fund for continued works on this Priority Strategy. (Reference: Report by Executive Director with responsibility for Roads and Infrastructure Services dated June 2025, submitted)
Word for word from the decision Argyll and Bute published for this meeting.Source: www.argyll-bute.gov.uk
Report to Environment, Development and Infrastructure Committee
Recommendations
2.1It is recommended that the Environment, Development and Infrastructure Committee:-
(a) Agree that funds are allocated as follows:- i. engage with suitable contractors to realise on-site accommodation at Port Askaig; ii. to engage with suitable Naval Architects to develop a ‘keel ready’ concept design for the Eilean Dhiura replacement ferry; iii. funds to engage with suitable consultants to update and progress plans for the Cuan ferry infrastructure for use by the Eilean Dhiura and Belnahua vessels; and
(b) In the event that part of the grant remains, approve ringfencing the fund for continued works on this Priority Strategy.
3.0DETAIL
3.1In 2024 Argyll and Bute Council was contacted by HITRANS and informed that £1,564,000 grant funds had been identified to support capital investment across Argyll and Bute Council’s internal ferry operations, including the Cuan Sound and Jura services. 3.2 The funds had been held for some time in a transaction between Strathclyde Partnership for Transport (SPT) and HITRANS, however following accounting and auditing checks this is now available for allocation to suitable projects with Argyll and Bute Council’s internal ferry operations. 3.3 In September 2024 the Environment, Development and Infrastructure Committee “approved the vessel priority strategy as illustrated in table 2 at 3.4 of the submitted report” reproduced below as Table 1.
Table 1 Vessel Priority Strategy
Priority Description Benefits 1 On-site accommodation at Port Askaig. Along with the market supplement Present situation requires Officers and and the 7-day rota, this will allow crew to be residents of Islay as well as the recruitment of suitably suitably qualified. certified Officers required for resilience and new vessel minimum manning levels. 2 Funding for concept design to ‘Keel To identify capacity levels; fuel Ready’ for the new Jura vessel. type; crew size and infrastructure upgrade requirements. Also allows for a more accurate assessment / estimate of build & certification costs. 3 Jura New Build (and associated Fit for purpose and the future infrastructure at Feolin & Port Askaig). vessel to support the Jura community for the next 20 – 30 years. 4 Eilean Dhiura is re-deployed to the A marked upgrade for the island Cuan / Luing route (and associated capable of refuse collection, HGV slipway upgrades on the route). and capacity increase from c.15t to c.40t. Due to life extension on Belnahua (2024) and Eilean Dhiura (2022) service expects to make savings by utilising Belnahua as relief vessel (for Dry dock) etc. 5 Easdale work boat replacement with TBD landing craft type vessel.
3.4Members are asked to align and allocate funds to the previously agreed priorities as follows: 1. Engage with suitable contractors to realise on-site accommodation at Port Askaig, 2. Engage with suitable Naval Architects to develop a ‘keel ready’ concept design for the Eilean Dhiura replacement ferry, and 3. Engage with suitable consultants to update and progress plans for the Cuan ferry infrastructure for use by the Eilean Dhiura and Belnahua vessels. 3.5 In the event that monies remain following these aspects of the plan, it is proposed that the funds remain available for allocation towards the next steps which along with sourcing additional funding, would include infrastructure design for Port Askaig and Feolin; tender preparation for shipyards; land purchases; construction of Cuan slipways and consultant project management.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Environment, Development and Infrastructure Committee at Argyll and Bute and we tell you when its next papers are published, before the meeting rather than after it.
Review of public convenience estateDecision The Environment, Development and Infrastructure Committee – 1. noted the findings of the updated baseline re...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.